The Hook Lab / Tracker / Asia / Malaysia Updated 2026-11-25
Tracker · Malaysia

Who's connected. Who's waiting. Who's gone.

110projects49with a sourced history6,814 MWrequested · projects with history

GridsTNB TNB (Peninsular Malaysia) · 45SEB Sarawak Energy · 3SESB Sabah Electricity · 01 with the grid not settled yetMalaysia is in progress: 110 projects, 49 with a sourced history so far.

Grid
State or province
History
Phase
Stage

Projects with a sourced history only

Size
Owner

110 projects

Evidence OwnerPlaceGrid Status
20202022202420262028
SourceDetails
Area Group Delapan data centre campusIn development Delapan (156 acres in two parcels), Kedah, Kedah TNB — Under construction 2026-10-15 DCD2 sources · medium
Open DC PE2 PenangNew · 2026 Bayan Lepas (10-acre converted factory), Penang TNB 100 MW Energisedfirst power 2026-09 2026-09-23 Tech Wire Asia2 sources · medium
Bridge Data Centres MY07Operating Desa Cemerlang, Ulu Tiram, Johor TNB 400 MW Connection offeredconnection offered 2026-09 2026-09-14 DCD1 source · low
Digital Halo JHB1In development Nusa Cemerlang Industrial Park, Iskandar Puteri (20.46 acres), Johor TNB — Announced 2026-09-14 DCD2 sources · medium
Vantage KUL1 Cyberjaya campusNew · 2025 Cyberjaya (6 acres; KUL11-KUL14), Selangor TNB — stage not on record 2026-09-14 DCD1 source · low
YTL-JLand STeP West campusIn development Sedenak Tech Park West, Ibrahim Technopolis, Johor TNB 1,500 MW Announced 2026-08-19 ytlpowerinternational.com2 sources · medium
SIC Quantum Data CentreIn development Cyberjaya, Selangor TNB 65 MW Announced 2026-08-11 robusthpc.com2 sources · medium
DPS Resources Bukit Rambai AI data centreIn development Lot 76, Kawasan Perindustrian Bukit Rambai (20 acres), Melaka TNB 88 MW Planning lodgedwaiting 4 moplanning lodged 2026-08 2026-08-104 mo koa.international1 source · low
GDC Banting data centreIn development COMPASS @ Kota Seri Langat industrial park, Banting (36 acres), Selangor TNB 210 MW Announced 2026-07-08 DCD1 source · low
DayOne Kapar siteIn development Mukim Kapar, Klang (three contiguous parcels, 157 acres), Selangor TNB — Announced 2026-07-06 edgeprop.my1 source · low
MRCB Bukit Jalil AI-ready data centreIn development Bukit Jalil (37,320 sq m plot), Kuala Lumpur TNB 65 MW Announced 2026-06-16 The Star1 source · low
Tanco and China Mobile International Port Dickson data centreIn development Port Dickson, Negeri Sembilan TNB 50 MW Announced 2026-06-09 moomoo.com2 sources · medium
Digital Realty Cyberjaya KUL10/KUL11Operating Cyberjaya, Selangor TNB — stage not on record 2026-06-09 datacenters.economictimes.indiatimes.com3 sources · medium
Equinix KL2In development Cyberjaya (14,300 sq m plot, under 1 km from KL1), Selangor TNB — Announced 2026-05-12 Equinix2 sources · high
Empyrion Digital MY1 Johor campusIn development SiLC industrial cluster, Iskandar Puteri (34.9 acres), Johor TNB 200 MW Connection offeredconnection offered 2026-05 2026-05-07 DCD2 sources · medium
Kuching AI Data CampusIn development Tanjung Embang, Samarahan, Sarawak SEB — Announced 2026-05-02 The Star1 source · low
AirTrunk JHB3 and JHB4In development Iskandar Puteri (near JHB1/JHB2), Johor TNB 280 MW Announced 2026-04-30 dcatlas.io2 sources · medium
Bridge Data Centres Banting campusIn development Banting (136 acres from IOI Properties), Selangor TNB — Announced 2026-02-06 DCD1 source · low
AIMS Cyberjaya 200MW AI data centreIn development Cyberjaya (~10 acres from Cyberview), Selangor TNB 200 MW Announced 2026-02-05 digitalnewsasia.com3 sources · medium
STT GDC STT Johor 1 campusIn development Nusa Cemerlang Industrial Park, Iskandar Puteri (22 acres), Johor TNB — Under construction 2026-02 DCD7 sources · high
Nexus Yang Green Data Centre campusIn development NS Semiconductor Valley Industrial Park (157 acres), Negeri Sembilan TNB 350 MW Under construction 2026-01-27 mcigroup.my2 sources · medium
TM Nxera Johor campusIn development Iskandar Puteri (JS-SEZ), Johor TNB — Under constructionconnection offered 2026-01 2026-01-12 The Star5 sources · high
Vantage JHB1New · 2025 Sedenak Tech Park, Kulai (72.8 acres; JS-SEZ), Johor TNB — Energisedfirst power 2025-06 2025-11 coloprice.com3 sources · medium
Baram DeepTech green data centre parkIn development Baram (350 acres), Sarawak SEB 200 MW Announced 2025-09-26 quiverquant.com2 sources · medium
UEM Sunrise and Logos Gerbang Nusajaya campus Gerbang Nusajaya, Iskandar Puteri, Johor TNB 360 MW Cancelledwithdrawn by proponentstage not on record 2025-06-25 Free Malaysia Today1 source · low
EdgeConneX Cyberjaya campusIn development Cyberjaya (nine buildings on ~30 acres), Selangor TNB 200 MW Announced 2025-04-24 Tech Wire Asia1 source · low
AirTrunk JHB2In development Iskandar Puteri (Johor Bahru), Johor TNB 270 MW Announced 2025-02-17 AirTrunk3 sources · high
STACK Infrastructure JHB01In development Iskandar Puteri (10.8 ha), Johor TNB 220 MW Announced 2025-01-14 STACK Infrastructure2 sources · high
Privasia Silverstreams data centreIn development Bagan Datuk (49 acres), Perak TNB — Announced 2024-12-11 theedgemalaysia.com1 source · low
NTT DATA Johor Bahru JHB10In development Gelang Patah, Johor TNB 290 MW Announced 2024-12-05 NTT DATA1 source · medium
GDC Kulim KLM1In development Jalan Hi-Tech 6/1, Kulim Hi-Tech Park (4.57 acres), Kedah TNB — Announced 2024-12-05 theedgemalaysia.com1 source · low
Google Elmina Business Park DC 2In development Elmina Business Park (77 acres), Selangor TNB — Announced 2024-11-30 klse.i3investor.com1 source · low
Perlis Advance Tech ParkIn development Chuping, Perlis TNB 1,250 MW Announced 2024-11-16 skyvast.co3 sources · high
Google Elmina Business Park DC 1In development Elmina Business Park (49 acres), Selangor TNB — Under construction 2024-10-01 simedarbyproperty.com4 sources · high
Oracle Malaysia cloud regionIn development Location not disclosed, Malaysia — — Announced 2024-10 mida.gov.my2 sources · high
Vantage KUL2 Cyberjaya campusIn development Cyberjaya (35 acres next to KUL1), Selangor TNB 256 MW Under construction 2024-08-06 Vantage4 sources · high
AWS Asia PacificOperating since 2024 Sites not disclosed (Klang Valley presumed), Selangor/KL TNB — Energisedfirst power 2024-08 2024-08 mida.gov.my1 source · medium
AirTrunk JHB1Operating since 2024 Iskandar Puteri (Johor Bahru), Johor TNB 150 MW Energisedfirst power 2024-07 2024-07-31 tnb.com.my1 source · medium
Equalbase Sunway City Iskandar Puteri DC landIn development Sunway City Iskandar Puteri (64 acres), Johor TNB — Announced 2024-07-03 digitalnewsasia.com1 source · low
TM Iskandar Puteri Core Data CentreOperating since 2017 Nusajaya Tech Park, Iskandar Puteri, Johor TNB — Announced 2024-06-18 mida.gov.my1 source · medium
Pi Data Centre CyberjayaIn development Persiaran Rimba Permai, Cyber 10, Cyberjaya, Selangor TNB — Announced 2024-06-01 mida.gov.my1 source · medium
Mah Sing DC Hub @ Southville CityIn development Southville City (KL South), Selangor TNB — Announced 2024-05-30 mida.gov.my4 sources · high
Bridge Data Centres MY02 CyberjayaIn development Cyberjaya (land with Cyberview), Selangor TNB — Announced 2024-02-29 mida.gov.my2 sources · high
EdgeConneX Kuala Lumpur CBDIn development Kuala Lumpur central business district, Kuala Lumpur TNB — Announced 2023-09-11 EdgeConneX1 source · medium
FutureData Sarawak data centre parkIn development Kota Samarahan (135 acres), Sarawak SEB — Announced 2023-06-26 DCD1 source · low
Bridge Data Centres MY06Operating since 2022 Sedenak Tech Park, Kulai, Johor TNB 110 MW Energisedfirst power 2022-10 2022-10-20 DCD2 sources · medium
ByteDance Sedenak expansionOperating since 2022 Sedenak Tech Park, Kulai, Johor TNB — Energisedfirst power 2022-10 2022-10-20 DCD1 source · low
NTT Cyberjaya campusOperating since 2023 Cyberjaya, Selangor TNB — Under construction 2022-09-05 mida.gov.my1 source · medium
YTL Green Data Center ParkOperating since 2024 Kulai (1,640-acre park), Johor TNB — Under construction 2022-08-25 mida.gov.my3 sources · high
Edra Melaka AI data centre ecosystemIn development Melaka (near the Edra power plant), Melaka TNB 2,000 MW Planned dagangnews.com1 source
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

110 projects, 49 with a sourced history. Every project has a page: what its first source reported, and each step of its history with the source and quote it rests on, marked confirmed (a primary source, or two sites) or 1 source. MW totals count projects with a history; medians use confirmed dates only.

No register lists every data centre, so this one grows from public sources. Know a project that is missing, or see an error? Tell us, with a link to a public source.

Comparables

49projects
—planning lodged → approved · n=0
—application → offer · n=0
—offer → first power · n=0
—planning lodged → first power · n=0