The Hook Lab / Tracker / Asia / Malaysia
Updated 2026-11-25
Tracker · Malaysia
Who's connected. Who's waiting. Who's gone.
110projects49with a sourced history6,814 MWrequested · projects with history
GridsTNB TNB (Peninsular Malaysia) · 45SEB Sarawak Energy · 3SESB Sabah Electricity · 01 with the grid not settled yetMalaysia is in progress: 110 projects, 49 with a sourced history so far.
| Evidence | Owner | Place | Grid | Status | 20202022202420262028 | Source | Details | |||
|---|---|---|---|---|---|---|---|---|---|---|
| Area Group Delapan data centre campusIn development | Delapan (156 acres in two parcels), Kedah, Kedah | TNB | — | Under construction | 2026-10-15 | DCD2 sources · medium | ||||
| Open DC PE2 PenangNew · 2026 | Bayan Lepas (10-acre converted factory), Penang | TNB | 100 MW | Energisedfirst power 2026-09 | 2026-09-23 | Tech Wire Asia2 sources · medium | ||||
| Bridge Data Centres MY07Operating | Desa Cemerlang, Ulu Tiram, Johor | TNB | 400 MW | Connection offeredconnection offered 2026-09 | 2026-09-14 | DCD1 source · low | ||||
| Digital Halo JHB1In development | Nusa Cemerlang Industrial Park, Iskandar Puteri (20.46 acres), Johor | TNB | — | Announced | 2026-09-14 | DCD2 sources · medium | ||||
| Vantage KUL1 Cyberjaya campusNew · 2025 | Cyberjaya (6 acres; KUL11-KUL14), Selangor | TNB | — | stage not on record | 2026-09-14 | DCD1 source · low | ||||
| YTL-JLand STeP West campusIn development | Sedenak Tech Park West, Ibrahim Technopolis, Johor | TNB | 1,500 MW | Announced | 2026-08-19 | ytlpowerinternational.com2 sources · medium | ||||
| SIC Quantum Data CentreIn development | Cyberjaya, Selangor | TNB | 65 MW | Announced | 2026-08-11 | robusthpc.com2 sources · medium | ||||
| DPS Resources Bukit Rambai AI data centreIn development | Lot 76, Kawasan Perindustrian Bukit Rambai (20 acres), Melaka | TNB | 88 MW | Planning lodgedwaiting 4 moplanning lodged 2026-08 | 2026-08-104 mo | koa.international1 source · low | ||||
| GDC Banting data centreIn development | COMPASS @ Kota Seri Langat industrial park, Banting (36 acres), Selangor | TNB | 210 MW | Announced | 2026-07-08 | DCD1 source · low | ||||
| DayOne Kapar siteIn development | Mukim Kapar, Klang (three contiguous parcels, 157 acres), Selangor | TNB | — | Announced | 2026-07-06 | edgeprop.my1 source · low | ||||
| MRCB Bukit Jalil AI-ready data centreIn development | Bukit Jalil (37,320 sq m plot), Kuala Lumpur | TNB | 65 MW | Announced | 2026-06-16 | The Star1 source · low | ||||
| Tanco and China Mobile International Port Dickson data centreIn development | Port Dickson, Negeri Sembilan | TNB | 50 MW | Announced | 2026-06-09 | moomoo.com2 sources · medium | ||||
| Digital Realty Cyberjaya KUL10/KUL11Operating | Cyberjaya, Selangor | TNB | — | stage not on record | 2026-06-09 | datacenters.economictimes.indiatimes.com3 sources · medium | ||||
| Equinix KL2In development | Cyberjaya (14,300 sq m plot, under 1 km from KL1), Selangor | TNB | — | Announced | 2026-05-12 | Equinix2 sources · high | ||||
| Empyrion Digital MY1 Johor campusIn development | SiLC industrial cluster, Iskandar Puteri (34.9 acres), Johor | TNB | 200 MW | Connection offeredconnection offered 2026-05 | 2026-05-07 | DCD2 sources · medium | ||||
| Kuching AI Data CampusIn development | Tanjung Embang, Samarahan, Sarawak | SEB | — | Announced | 2026-05-02 | The Star1 source · low | ||||
| AirTrunk JHB3 and JHB4In development | Iskandar Puteri (near JHB1/JHB2), Johor | TNB | 280 MW | Announced | 2026-04-30 | dcatlas.io2 sources · medium | ||||
| Bridge Data Centres Banting campusIn development | Banting (136 acres from IOI Properties), Selangor | TNB | — | Announced | 2026-02-06 | DCD1 source · low | ||||
| AIMS Cyberjaya 200MW AI data centreIn development | Cyberjaya (~10 acres from Cyberview), Selangor | TNB | 200 MW | Announced | 2026-02-05 | digitalnewsasia.com3 sources · medium | ||||
| STT GDC STT Johor 1 campusIn development | Nusa Cemerlang Industrial Park, Iskandar Puteri (22 acres), Johor | TNB | — | Under construction | 2026-02 | DCD7 sources · high | ||||
| Nexus Yang Green Data Centre campusIn development | NS Semiconductor Valley Industrial Park (157 acres), Negeri Sembilan | TNB | 350 MW | Under construction | 2026-01-27 | mcigroup.my2 sources · medium | ||||
| TM Nxera Johor campusIn development | Iskandar Puteri (JS-SEZ), Johor | TNB | — | Under constructionconnection offered 2026-01 | 2026-01-12 | The Star5 sources · high | ||||
| Vantage JHB1New · 2025 | Sedenak Tech Park, Kulai (72.8 acres; JS-SEZ), Johor | TNB | — | Energisedfirst power 2025-06 | 2025-11 | coloprice.com3 sources · medium | ||||
| Baram DeepTech green data centre parkIn development | Baram (350 acres), Sarawak | SEB | 200 MW | Announced | 2025-09-26 | quiverquant.com2 sources · medium | ||||
| UEM Sunrise and Logos Gerbang Nusajaya campus | Gerbang Nusajaya, Iskandar Puteri, Johor | TNB | 360 MW | Cancelledwithdrawn by proponentstage not on record | 2025-06-25 | Free Malaysia Today1 source · low | ||||
| EdgeConneX Cyberjaya campusIn development | Cyberjaya (nine buildings on ~30 acres), Selangor | TNB | 200 MW | Announced | 2025-04-24 | Tech Wire Asia1 source · low | ||||
| AirTrunk JHB2In development | Iskandar Puteri (Johor Bahru), Johor | TNB | 270 MW | Announced | 2025-02-17 | AirTrunk3 sources · high | ||||
| STACK Infrastructure JHB01In development | Iskandar Puteri (10.8 ha), Johor | TNB | 220 MW | Announced | 2025-01-14 | STACK Infrastructure2 sources · high | ||||
| Privasia Silverstreams data centreIn development | Bagan Datuk (49 acres), Perak | TNB | — | Announced | 2024-12-11 | theedgemalaysia.com1 source · low | ||||
| NTT DATA Johor Bahru JHB10In development | Gelang Patah, Johor | TNB | 290 MW | Announced | 2024-12-05 | NTT DATA1 source · medium | ||||
| GDC Kulim KLM1In development | Jalan Hi-Tech 6/1, Kulim Hi-Tech Park (4.57 acres), Kedah | TNB | — | Announced | 2024-12-05 | theedgemalaysia.com1 source · low | ||||
| Google Elmina Business Park DC 2In development | Elmina Business Park (77 acres), Selangor | TNB | — | Announced | 2024-11-30 | klse.i3investor.com1 source · low | ||||
| Perlis Advance Tech ParkIn development | Chuping, Perlis | TNB | 1,250 MW | Announced | 2024-11-16 | skyvast.co3 sources · high | ||||
| Google Elmina Business Park DC 1In development | Elmina Business Park (49 acres), Selangor | TNB | — | Under construction | 2024-10-01 | simedarbyproperty.com4 sources · high | ||||
| Oracle Malaysia cloud regionIn development | Location not disclosed, Malaysia | — | — | Announced | 2024-10 | mida.gov.my2 sources · high | ||||
| Vantage KUL2 Cyberjaya campusIn development | Cyberjaya (35 acres next to KUL1), Selangor | TNB | 256 MW | Under construction | 2024-08-06 | Vantage4 sources · high | ||||
| AWS Asia PacificOperating since 2024 | Sites not disclosed (Klang Valley presumed), Selangor/KL | TNB | — | Energisedfirst power 2024-08 | 2024-08 | mida.gov.my1 source · medium | ||||
| AirTrunk JHB1Operating since 2024 | Iskandar Puteri (Johor Bahru), Johor | TNB | 150 MW | Energisedfirst power 2024-07 | 2024-07-31 | tnb.com.my1 source · medium | ||||
| Equalbase Sunway City Iskandar Puteri DC landIn development | Sunway City Iskandar Puteri (64 acres), Johor | TNB | — | Announced | 2024-07-03 | digitalnewsasia.com1 source · low | ||||
| TM Iskandar Puteri Core Data CentreOperating since 2017 | Nusajaya Tech Park, Iskandar Puteri, Johor | TNB | — | Announced | 2024-06-18 | mida.gov.my1 source · medium | ||||
| Pi Data Centre CyberjayaIn development | Persiaran Rimba Permai, Cyber 10, Cyberjaya, Selangor | TNB | — | Announced | 2024-06-01 | mida.gov.my1 source · medium | ||||
| Mah Sing DC Hub @ Southville CityIn development | Southville City (KL South), Selangor | TNB | — | Announced | 2024-05-30 | mida.gov.my4 sources · high | ||||
| Bridge Data Centres MY02 CyberjayaIn development | Cyberjaya (land with Cyberview), Selangor | TNB | — | Announced | 2024-02-29 | mida.gov.my2 sources · high | ||||
| EdgeConneX Kuala Lumpur CBDIn development | Kuala Lumpur central business district, Kuala Lumpur | TNB | — | Announced | 2023-09-11 | EdgeConneX1 source · medium | ||||
| FutureData Sarawak data centre parkIn development | Kota Samarahan (135 acres), Sarawak | SEB | — | Announced | 2023-06-26 | DCD1 source · low | ||||
| Bridge Data Centres MY06Operating since 2022 | Sedenak Tech Park, Kulai, Johor | TNB | 110 MW | Energisedfirst power 2022-10 | 2022-10-20 | DCD2 sources · medium | ||||
| ByteDance Sedenak expansionOperating since 2022 | Sedenak Tech Park, Kulai, Johor | TNB | — | Energisedfirst power 2022-10 | 2022-10-20 | DCD1 source · low | ||||
| NTT Cyberjaya campusOperating since 2023 | Cyberjaya, Selangor | TNB | — | Under construction | 2022-09-05 | mida.gov.my1 source · medium | ||||
| YTL Green Data Center ParkOperating since 2024 | Kulai (1,640-acre park), Johor | TNB | — | Under construction | 2022-08-25 | mida.gov.my3 sources · high | ||||
| Edra Melaka AI data centre ecosystemIn development | Melaka (near the Edra power plant), Melaka | TNB | 2,000 MW | Planned | dagangnews.com1 source | |||||
| No projects match. | ||||||||||
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
110 projects, 49 with a sourced history. Every project has a page: what its first source reported, and each step of its history with the source and quote it rests on, marked confirmed (a primary source, or two sites) or 1 source. MW totals count projects with a history; medians use confirmed dates only.
No register lists every data centre, so this one grows from public sources. Know a project that is missing, or see an error? Tell us, with a link to a public source.
Comparables
49projects
—planning lodged → approved · n=0
—application → offer · n=0
—offer → first power · n=0
—planning lodged → first power · n=0