The Hook Lab / Tracker / Asia / Malaysia / ByteDance Sedenak expansion Updated 2026-11-25
Tracker · Malaysia · TNB · Johor

ByteDance Sedenak expansion

ByteDance System Sdn Bhd · Sedenak Tech Park, Kulai, Johor

Energisedchanged 2022-10-20
—requested
—offered
—energised
—closed
lowconfidence · 1 source
Market
Malaysia · Asia
Grid
TNB · TNB (Peninsular Malaysia)
Place
Sedenak Tech Park, Kulai, Johor
Network
—
First power
2022-10-20
First reported by
businesstoday.com.my · no status given
Dates it gives
MITI statement 2024-06-07: RM10bn AI investment incl. RM1.5bn expansion of existing Sedenak DC

Who is on it

Developer
Bridge Data Centres · mida.gov.my
Tenant
ByteDance System Sdn. Bhd. · mida.gov.my
Tenant
ByteDance · datacenterdynamics.com

Timeline

2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2022-10-20date: document dateon or before
    stageEnergised1 source
    • DCD press
      The ChinData-owned company, together with ByteDance, this week announced the opening of the first phase of the MY06 data center in Sedenak.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.