Cancelledwithdrawn by proponentstage not on recordchanged 2025-06-25
360 MWrequested
—offered
—energised
—closed
lowconfidence · 1 source
- Market
- Malaysia · Asia
- Grid
- TNB · TNB (Peninsular Malaysia)
- Place
- Gerbang Nusajaya, Iskandar Puteri, Johor
- Network
- —
- First reported by
- Free Malaysia Today · cancelled
- Dates it gives
- MoU 2024-05
lapsed after Logos ownership change
confirmed scrapped 2025-06-25
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2025-06-25date: document dateon or before
conditionCancelled1 sourcewithdrawn by proponent
- Free Malaysia Today press
UEM Sunrise Bhd’s deal to build a data centre campus in Gerbang Nusajaya, Johor, with Singapore firm Logos Infrastructure Holdco Pte Ltd has been scrapped.
- Free Malaysia Today press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.