The Hook Lab / Tracker / Asia / Malaysia / TM Nxera Johor campus Updated 2026-11-25
Tracker · Malaysia · TNB · Johor

TM Nxera Johor campus

TM Nxera · Iskandar Puteri (JS-SEZ), Johor

Under constructionchanged 2026-01-12
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 5 sources
Market
Malaysia · Asia
Grid
TNB · TNB (Peninsular Malaysia)
Place
Iskandar Puteri (JS-SEZ), Johor
Network
—
Announced
2024-06-18
Connection offered
2026-01-12
Construction started
2024-07-25
First reported by
The Star · under construction
Dates it gives
JV announced 2024-06-18
groundbreaking 2024-07
ESA 2026-01-12
topped out 2026-04-16
phase 1 RFS 2026

Who is on it

Developer
Nxera · mida.gov.my

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-01-12date: document dateon or before
    stageConnection offered1 source
    • The Star press
      TM Nxera has signed a multi-year electricity supply agreement with Tenaga Nasional (TNB) to secure 280 megawatt (MW) for its hyperconnected, AI-ready data centre campus in Iskandar Puteri, Johor.
  2. 2024-07-25
    stageUnder constructionconfirmed
    • mida.gov.my primary
      TM, Singtel’s Nxera break ground for state-of-the-art, AI-ready data centre campus in Johor
    • mida.gov.my primary
      In a report last Friday (July 26), the firm said that Telekom Malaysia Bhd (KL:TM) and Nxera — the Digital InfraCo unit of SingTel — have begun constructing a sustainable, AI-grade data centre in Johor.
  3. 2024-06-18
    stageAnnouncedconfirmed
    • mida.gov.my primary
      Telekom Malaysia Bhd (TM) is partnering Nxera, the regional data centre arm of Singapore’s Singtel’s Digital InfraCo unit, to develop data centres in Malaysia starting with a sustainable, hyper-connected artificial intelligence (AI)-ready data centre campus in Johor.
    • mida.gov.my primary
      Telekom Malaysia Bhd and Singapore Telecommunications Ltd’s announcement on June 18, which was to develop a hyper-connected artificial intelligence-ready data centre campus in Johor with an initial capacity of 64 megawatt (MW) – potentially to be scaled up to 200MW.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.