The Hook Lab / Tracker / Asia / Malaysia / Pi Data Centre Cyberjaya Updated 2026-11-25
Tracker · Malaysia · TNB · Selangor

Pi Data Centre Cyberjaya

Pi Data Centre Sdn Bhd · Persiaran Rimba Permai, Cyber 10, Cyberjaya, Selangor

Announcedchanged 2024-06-01
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
Market
Malaysia · Asia
Grid
TNB · TNB (Peninsular Malaysia)
Place
Persiaran Rimba Permai, Cyber 10, Cyberjaya, Selangor
Network
—
Announced
2024-06-01
First reported by
Baxtel · no status given
Dates it gives
phase 1 construction scheduled 2024-Q3 to 2025-Q4

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2024-06-01
    stageAnnouncedconfirmed
    • mida.gov.my primary
      Jakel Group is partnering with PiDC Holding Bhd to build a 51MW data centre in Cyberjaya worth RM1.2 billion.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error