The Hook Lab / Tracker / Asia / Malaysia / EdgeConneX Kuala Lumpur CBD
Updated 2026-11-25
Tracker · Malaysia · TNB · Kuala Lumpur
EdgeConneX Kuala Lumpur CBD
EdgeConneX · Kuala Lumpur central business district, Kuala Lumpur
Announcedchanged 2023-09-11
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
- Market
- Malaysia · Asia
- Grid
- TNB · TNB (Peninsular Malaysia)
- Place
- Kuala Lumpur central business district, Kuala Lumpur
- Network
- —
- Announced
- 2023-09-11
- First reported by
- EdgeConneX · no status given
- Dates it gives
- announced 2023-09-11
Timeline
2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2023-09-11
stageAnnouncedconfirmed
- EdgeConneX primary
EdgeConneX®, the pioneer in global Hyperlocal to Hyperscale Data Center Solutions announces its entrance into the Malaysian market with plans to build highly proximate and high-power data centers that will deliver nearly 300 MWs of capacity combined.
- EdgeConneX primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.