The Hook Lab / Tracker / Asia / Malaysia / Area Group Delapan data centre campus
Updated 2026-11-25
Tracker · Malaysia · TNB · Kedah
Area Group Delapan data centre campus
Area Group · Delapan (156 acres in two parcels), Kedah, Kedah
Under constructionchanged 2026-10-15
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- Malaysia · Asia
- Grid
- TNB · TNB (Peninsular Malaysia)
- Place
- Delapan (156 acres in two parcels), Kedah, Kedah
- Network
- —
- Announced
- 2024-10-10
- Construction started
- 2026-10-15
- First reported by
- Baxtel · under construction
- Dates it gives
- construction start reported 2024-10
first data centre expected end 2025
Who is on it
- Developer
- Northern Gateway Sdn Bhd · delapan.my
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-10-15date: document dateon or before
stageUnder construction1 source
- DCD press
Area Group has now officially purchased the land in a sale and purchase agreement for an undisclosed amount, and begun construction on the first 30-acre parcel of land.
- DCD press
-
2024-10-10
stageAnnounced1 source
- delapan.my press
The AREA Group (AREA) through its SPV; Data Gateway S/B signed an SPA today with Northern Gateway S/B (NGX) initiating the first phase of the development of a hyperscale Data Centre Campus, the AREA Data Centre Campus (ADCC) at Delapan in Kedah.
- delapan.my press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.