STACK Infrastructure JHB01

STACK Infrastructure · Iskandar Puteri (10.8 ha), Johor

Announcedchanged 2025-01-14
220 MWrequested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
Market
Malaysia · Asia
Grid
TNB · TNB (Peninsular Malaysia)
Place
Iskandar Puteri (10.8 ha), Johor
Network
—
Announced
2025-01-14
First reported by
DCD · under construction
Dates it gives
Announced 2025-01-14
first phase initial delivery Q4 2026

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2025-01-14
    stageAnnouncedconfirmed
    • STACK Infrastructure primary
      The new 220MW campus in Johor Bahru’s Iskandar Puteri expands STACK’s footprint to the largest market in Southeast Asia
    • DCD press
      Announced this week, the 10.8-hectare campus will span two facilities and 1 million sq ft (92,900 sqm).

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.