The Hook Lab / Tracker / Asia / Malaysia / Bridge Data Centres MY06
Updated 2026-11-25
Tracker · Malaysia · TNB · Johor
Bridge Data Centres MY06
Bridge Data Centres · Sedenak Tech Park, Kulai, Johor
Energisedchanged 2022-10-20
110 MWrequested
—offered
—energised
—closed
mediumconfidence · 2 sources
- Market
- Malaysia · Asia
- Grid
- TNB · TNB (Peninsular Malaysia)
- Place
- Sedenak Tech Park, Kulai, Johor
- Network
- —
- Announced
- 2021-12-31
- First power
- 2022-10-20
- First reported by
- mida.gov.my · operating
- Dates it gives
- Groundbreaking 2021-11
phase 1 grand opening 2022-10-20
Who is on it
- Tenant
- ByteDance · datacenterdynamics.com
Timeline
20202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2022-10-20date: document dateon or before
stageEnergised1 source
- DCD press
The ChinData-owned company, together with ByteDance, this week announced the opening of the first phase of the MY06 data center in Sedenak.
- DCD press
-
≤ 2021-12-31on or before
stageAnnounced1 source
- DCD press
First announced in late 2021, phase 1 of the 110MW project covers the first of three buildings across the 38-acre site, located within the Sedenak Tech Park (STeP).
- DCD press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.