DPS Resources · Lot 76, Kawasan Perindustrian Bukit Rambai (20 acres), Melaka
Planning lodgedchanged 2026-08-10
88 MWrequested
—offered
—energised
4 mowaiting since first filing
lowconfidence · 1 source
- Market
- Malaysia · Asia
- Grid
- TNB · TNB (Peninsular Malaysia)
- Place
- Lot 76, Kawasan Perindustrian Bukit Rambai (20 acres), Melaka
- Network
- —
- Planning lodged
- 2026-08-10
- First reported by
- Baxtel · no status given
- Dates it gives
- planned year 2028
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-08-10date: document dateon or before
stagePlanning lodged1 source
- koa.international press
The application form, together with the relevant documents and support letter, has been submitted to the Data Centre Task Force as part of the application process.
- koa.international press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.