The Hook Lab / Tracker / Asia / Malaysia / FutureData Sarawak data centre park Updated 2026-11-25
Tracker · Malaysia · SEB · Sarawak

FutureData Sarawak data centre park

FutureData Sdn Bhd · Kota Samarahan (135 acres), Sarawak

Announcedchanged 2023-06-26
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
Malaysia · Asia
Grid
SEB · Sarawak Energy
Place
Kota Samarahan (135 acres), Sarawak
Network
—
Announced
2023-06-26
First reported by
Baxtel · under construction
Dates it gives
consortium formed 2023-06
construction start 2025-Q2
first data centre expected 2026

Timeline

2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2023-06-26date: document dateon or before
    stageAnnounced1 source
    • DCD press
      Singaporean engineering firm Cyclect Group and local conglomerate TSG Group this week announced the formation of FutureData Sdn Bhd, a new company that plans to build a 200MW data center in the Malaysian state of Sarawak, located on the northwest of Borneo Island.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error