Updated 2026-11-25
Tracker · Malaysia · SEB · Sarawak
FutureData Sarawak data centre park
FutureData Sdn Bhd · Kota Samarahan (135 acres), Sarawak
Announcedchanged 2023-06-26
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- Malaysia · Asia
- Grid
- SEB · Sarawak Energy
- Place
- Kota Samarahan (135 acres), Sarawak
- Network
- —
- Announced
- 2023-06-26
- First reported by
- Baxtel · under construction
- Dates it gives
- consortium formed 2023-06
construction start 2025-Q2
first data centre expected 2026
Timeline
2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2023-06-26date: document dateon or before
stageAnnounced1 source
- DCD press
Singaporean engineering firm Cyclect Group and local conglomerate TSG Group this week announced the formation of FutureData Sdn Bhd, a new company that plans to build a 200MW data center in the Malaysian state of Sarawak, located on the northwest of Borneo Island.
- DCD press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.