The Hook Lab / Tracker / Asia / Malaysia / MRCB Bukit Jalil AI-ready data centre Updated 2026-11-25
Tracker · Malaysia · TNB · Kuala Lumpur

MRCB Bukit Jalil AI-ready data centre

MRCB · Bukit Jalil (37,320 sq m plot), Kuala Lumpur

Announcedchanged 2026-06-16
65 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
Malaysia · Asia
Grid
TNB · TNB (Peninsular Malaysia)
Place
Bukit Jalil (37,320 sq m plot), Kuala Lumpur
Network
—
Announced
2026-06-16
First reported by
The Star · no status given
Dates it gives
collaboration reported 2026-06-16
definitive agreements expected 2026-Q3
completion targeted 2027-Q4

Who is on it

Developer
Bukit Jalil Sentral Property Sdn Bhd · thestar.com.my
Builder
Inspur Communication Malaysia Sdn Bhd · metproperty.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-06-16date: document dateon or before
    stageAnnounced1 source
    • The Star press
      Malaysian Resources Corp Bhd (MRCB) is entering a strategic collaboration with Perintis Akal Sdn Bhd, a unit of Pemandu Partners International PLT, to develop an AI-ready data centre facility in Bukit Jalil with an estimated gross development cost of RM2.1bil.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.