The Hook Lab / Tracker / Asia / Malaysia / Nexus Yang Green Data Centre campus
Updated 2026-11-25
Tracker · Malaysia · TNB · Negeri Sembilan
Nexus Yang Green Data Centre campus
Vena Nexus · NS Semiconductor Valley Industrial Park (157 acres), Negeri Sembilan
Under constructionchanged 2026-01-27
350 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- Malaysia · Asia
- Grid
- TNB · TNB (Peninsular Malaysia)
- Place
- NS Semiconductor Valley Industrial Park (157 acres), Negeri Sembilan
- Network
- —
- Construction started
- 2026-01-27
- First reported by
- thesun.my · under construction
- Dates it gives
- groundbreaking reported 2026-01-26
completion expected 2027-Q1
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-01-27date: document dateon or before
stageUnder constructionconfirmed
- mcigroup.my press
after officiating at the groundbreaking ceremony of the green data centre campus
- bernama.com press
after officiating at the groundbreaking ceremony of the green data centre campus
- mcigroup.my press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.