The Hook Lab / Tracker / North America / United States Updated 2026-11-25
Tracker · United States

Who's connected. Who's waiting. Who's gone.

1,488projects553with a sourced history105,164 MWrequested · projects with history

GridsERCOT ERCOT · 60PJM PJM · 171MISO MISO · 47SPP SPP · 11CAISO CAISO · 1NYISO NYISO · 3ISONE ISO New England · 3US-OTHER Other US (outside the ISOs) · 117140 with the grid not settled yetUnited States is in progress: 1,488 projects, 553 with a sourced history so far.

Grid
State or province
History
Phase
Stage

Projects with a sourced history only

Condition

Projects with a sourced history only

Size
Owner

1488 projects

Evidence OwnerPlaceGrid Status
20202022202420262028
SourceDetails
Pekin data centre proposal Pekin, IL MISO — Cancelledwithdrawn by proponentstage not on record 2026-11-12 constructionreviewonline.com2 sources · medium
Green Data Socorro County Socorro County, NM US-OTHER — AnnouncedCancelledwithdrawn by proponent 2026-11-11 morethanjustparks.com2 sources · medium
Jay data centreIn development Jay, ME ISONE — Planning lodgedPausedwithdrawn by proponentwaiting ≥ 0 moplanning lodged 2026-11 2026-11-10≥ 0 mo sunjournal.com5 sources · medium
Project Green MountainIn development Archbald, Lackawanna County, PA PJM — Planning lodgedwaiting ≥ 1 moplanning lodged 2026-11 2026-11-09≥ 1 mo thetimes-tribune.com2 sources · medium
Cochise Supercomputer CampusIn development near Cochise and the Apache Generating Station, Cochise County, AZ US-OTHER 6,000 MW Connection appliedwaiting 1 moplanning lodged 2026-11 · connection applied 2026-11 2026-11-061 mo cochise.az.gov3 sources · high
Amazon Somervell County data centre campusIn development Glen Rose area, Somervell County, TX ERCOT — Announced 2026-11-05 Amazon1 source · medium
Amazon Wharton County data centre campusIn development Boling, Wharton County, TX ERCOT — Planning lodgedwaiting 1 moplanning lodged 2026-10 2026-11-051 mo Amazon2 sources · high
Monarch Compute CampusIn development Point Pleasant, Mason County, WV PJM — Under construction 2026-11-05 nscale.com2 sources · high
Southeast Wyoming data centre campusIn development Southeast Wyoming, WY — — Announced 2026-11-05 blog.google1 source · medium
Auburndale Technology CenterIn development 810 Pace Road, Auburndale, Polk County, FL US-OTHER 700 MW Planning approvedwaiting 1 moplanning lodged 2026-11 · planning approved 2023-12 2026-11-041 mo How Auburndale Approved a Data Center in Polk County Without Ever Saying It Out Loud - NewsBreak5 sources · medium
EdgeConneX Ashville data centresIn development Ashville, OH PJM — Under construction 2026-11-04 stockanalysis.com3 sources · medium
West Richland Data Center CampusIn development West Richland, Benton County, WA US-OTHER 912 MW AnnouncedContestedcommunity opposition 2026-11-03 triyaknews.com2 sources · medium
Google Hermantown data centreIn development Hermantown, MN MISO — Planning approvedContestedplanning approved 2026-10 2026-10-31 mprnews.org3 sources · medium
TerraVolt Declo campusIn development near Declo, Cassia County, ID US-OTHER — Announced 2026-10-30 sec.gov3 sources · high
Prometheus Hyperscale Natrona County campus Natrona and Converse counties, near Casper, WY — — AnnouncedCancelledwithdrawn by proponent 2026-10-29 buffalobulletin.com3 sources · medium
Beltline Energy Oklahoma CityIn development Oklahoma City, near Yukon, OK — — Planning approvedplanning approved 2026-10 2026-10-27 news9.com1 source · low
Eatonton 379 Data Center campusIn development Glenwood Springs Road near Eatonton, Putnam County, GA US-OTHER 520 MW Planning lodgedwaiting 1 moplanning lodged 2026-10 2026-10-261 mo constructionreviewonline.com1 source · low
Roswell Information ParkIn development Roswell, NM — — Announced 2026-10-25 abqjournal.com1 source · low
T5@Chicago IVIn development Grayslake, Lake County, IL PJM — Connection offeredplanning approved 2026-09 · connection offered 2026-10 2026-10-25 everydatacenter.com5 sources · medium
Teraplex Gallup Tradeport Gallup, NM US-OTHER — AnnouncedCancelled 2026-10-25 abqjournal.com2 sources · medium
Google Van Buren Township data centreIn development Van Buren Township, MI — — Connection offeredplanning approved 2026-10 · connection offered 2025-12 2026-10-19 planetdetroit.org2 sources · high
Province Group Powhatan campusIn development Ellis Farm, 1318 Page Road, Powhatan County, VA PJM 300 MW Planning approvedwaiting 31 moplanning lodged 2024-05 · planning approved 2026-10 2026-10-1531 mo DCD2 sources · medium
Vantage RenoIn development Reno, NV — 224 MW Planning lodgedwaiting 1 moplanning lodged 2026-10 2026-10-151 mo DCD3 sources · medium
Village Place Technology ParkIn development Gainesville, Prince William County, VA PJM 210 MW Planning approvedplanning approved 2026-10 2026-10-15 DCD1 source · low
Cloud Centers Lisle data centreIn development Lisle, IL PJM 50 MW Planning lodgedwaiting 1 moplanning lodged 2026-10 2026-10-151 mo DCD1 source · low
Switch Foundry WestOperating Austin, TX ERCOT 44 MW Planning lodgedwaiting 1 moplanning lodged 2026-10 2026-10-151 mo DCD3 sources · high
Amazon Richmond County data centre campusIn development Richmond County, NC US-OTHER — Under construction 2026-10-15 DCD4 sources · high
AWS Homer City campusIn development Center and Blacklick townships, Indiana County, PA PJM — Planning lodgedwaiting 1 moplanning lodged 2026-10 2026-10-151 mo DCD2 sources · medium
DC BLOX NashvilleIn development Nashville, Davidson County, TN US-OTHER — Planning approvedContestedplanning approvalwaiting 1 moplanning lodged 2026-10 · planning approved 2026-10 2026-10-151 mo DCD4 sources · high
Diode Ventures Peculiar campusIn development Peculiar, MO — — Planning approvedplanning approved 2026-10 2026-10-15 DCD5 sources · medium
Gregory Road Data CenterIn development Gregory Road, Covington, Newton County, GA US-OTHER — Planning lodgedwaiting 1 moplanning lodged 2026-10 2026-10-151 mo DCD1 source · low
Microsoft Dorr Township siteIn development Dorr Township, MI — — Announced 2026-10-15 DCD1 source · low
Microsoft Elk Grove Village datacenterIn development Elk Grove Village, IL PJM — Under constructionwaiting 1 moplanning lodged 2026-10 2026-10-151 mo DCD2 sources · medium
Microsoft Wellington datacenter siteIn development Prince William County, VA PJM — Planning lodgedwaiting 1 moplanning lodged 2026-10 2026-10-151 mo DCD1 source · low
Provident Chesterton data centreIn development Chesterton, Porter County, IN MISO — Contestedcommunity oppositionstage not on record 2026-10-15 DCD2 sources · medium
Riot Corsicana campusOperating Corsicana, Navarro County, TX ERCOT — Planning lodgedwaiting 1 moplanning lodged 2026-10 2026-10-151 mo DCD5 sources · high
STACK Berry Hill megasite campusIn development Berry Hill megasite, Pittsylvania County, VA PJM — Announced 2026-10-15 DCD1 source · low
Stargate Milam CountyIn development Milam County, TX — — Under construction 2026-10-15 datacenterriskatlas.org1 source · low
Vantage Pittsboro data centreIn development Pittsboro (north of I-74, west of CR 500 East), Hendricks County, IN MISO — Planning approvedwaiting 1 moplanning lodged 2026-10 · planning approved 2025-03 2026-10-151 mo DCD3 sources · medium
Accokeek Center data campusIn development Falmouth District, Stafford County, VA PJM — Planning approvedplanning approved 2026-10 2026-10-08 Potomac Local1 source · low
Big Woods Technology ParkIn development near Bassfield, Jefferson Davis County, MS — — Announced 2026-10-07 mississippifreepress.org1 source · low
5C MEM01Operating 4300 Getwell Road, Memphis, Shelby County, TN US-OTHER 84 MW Planning approvedwaiting 2 moplanning lodged 2026-10 · planning approved 2025-04 2026-10-062 mo Data Center Frontier3 sources · medium
AVAIO Project HerculesIn development Appomattox Center for Business and Commerce, off US 460 and VA 26, Appomattox County, VA PJM 300 MW Planning approvedContestedcommunity oppositionplanning approved 2026-10 2026-10-05 Cardinal News4 sources · high
Grande Valley Industrial Data Center CampusIn development south-west of the Maricopa-Casa Grande Highway near Montgomery Road, Casa Grande, Pinal County, AZ US-OTHER — Planning approvedplanning approved 2026-10 2026-10-01 everydatacenter.com1 source · low
Vantage Trident Data CenterIn development E-470 and East 48th Avenue, Aurora, CO US-OTHER — Contestedcommunity oppositionstage not on record 2026-10-01 coloradopolitics.com1 source · low
Digital Realty KokomoIn development Industrial Park North, Kokomo, IN — 1,000 MW Announced 2026-10 DCD3 sources · high
Meta Mason County data centre campusIn development near Maysville, Mason County, KY — — Announced 2026-10 States Newsroom1 source · low
DC BLOX Thunderbird Data CenterIn development Indianapolis, Marion County, IN MISO — Under constructionplanning approved 2026-09 2026-09-30 thebutlercollegian.com2 sources · medium
Aerotropolis Logistics Center data centresIn development east of The Aurora Highlands, Aurora, CO US-OTHER — Planning lodgedwaiting 2 moplanning lodged 2026-09 2026-09-292 mo sentinelcolorado.com1 source · low
Amazon King George campusIn development Near Sealston, King George County, VA PJM — Planning approvedplanning approved 2026-09 2026-09-29 fredericksburgfreepress.com4 sources · medium
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

1488 projects, 553 with a sourced history. Every project has a page: what its first source reported, and each step of its history with the source and quote it rests on, marked confirmed (a primary source, or two sites) or 1 source. MW totals count projects with a history; medians use confirmed dates only.

No register lists every data centre, so this one grows from public sources. Know a project that is missing, or see an error? Tell us, with a link to a public source.

Comparables

553projects
7 moplanning lodged → approved · n=3
—application → offer · n=0
—offer → first power · n=0
—planning lodged → first power · n=0