Riot Corsicana campus

Riot Platforms · Corsicana, Navarro County, TX

Planning lodgedchanged 2026-10-15
—requested
—offered
—energised
1 mowaiting since first filing
highconfidence · 5 sources
Market
United States · North America
Grid
ERCOT · ERCOT
Place
Corsicana, Navarro County, TX
Network
—
Announced
2022-12-31
Planning lodged
2026-10-15
First reported by
Riot Platforms · operating
Dates it gives
construction began 2023
AI lease announced 2026-11-04

Who is on it

Owner
Riot Platforms, Inc. · sec.gov
Tenant
Anthropic PBC · sec.gov

Timeline

2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-10-15date: document dateon or before
    stagePlanning lodged1 source
    • DCD press
      The company recently filed with the Texas Department of Licensing and Regulation to develop a new data center building at its existing campus at 6980 FM 709 in Corsicana.
  2. 2025-01-21
    conditionPaused1 source
    • sec.gov primary
      In connection with its evaluation of AI/HPC opportunities, Riot is halting the development of its previously announced 600 MW Phase II Bitcoin mining expansion at the Corsicana Facility.
  3. ≤ 2024-12-31on or before
    milestoneExpandedconfirmed
    • sec.gov primary
      In 2024, we completed construction of 400 MW of developed capacity at our second large-scale data center in Navarro County, Texas (the “Corsicana Facility”).
  4. ≤ 2022-12-31on or before
    stageAnnouncedconfirmed
    • sec.gov primary
      During the year ended December 31, 2022, we announced the initiation of a large-scale development to expand our Bitcoin mining and data center hosting capabilities in Navarro County, Texas with the acquisition of a 265-acre site where the anticipated one-gigawatt Corsicana Facility is being constructed.
    • sec.gov primary
      In 2022, the Company initiated a large-scale development to expand its Bitcoin mining and data center hosting capabilities on a 265-acre site in Navarro County, Texas, strategically located next to the Navarro switch (the “Corsicana Facility”).

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.