The Hook Lab / Tracker / North America / United States / Digital Realty Kokomo Updated 2026-11-25
Tracker · United States · IN

Digital Realty Kokomo

Digital Realty · Industrial Park North, Kokomo, IN

Announcedchanged 2026-10
1,000 MWrequested
—offered
—energised
—waiting: no filing date on record
highconfidence · 3 sources
Market
United States · North America
Grid
not settled yet
Place
Industrial Park North, Kokomo, IN
Network
—
Announced
2026-10
First reported by
Digital Realty · planned

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-10
    stageAnnouncedconfirmed
    • DCD press
      The city of Kokomo first announced Digital's interest in developing in the city earlier this month.
    • datacenters.economictimes.indiatimes.com press
      Kokomo Mayor Tyler Moore announced the project during his State of the City address.
    • Digital Realty primary
      Our proposed data center project in Kokomo, Indiana, would bring lasting economic investment and opportunity to Industrial Park North, increasing demand for construction workers, skilled trades, and local suppliers while providing digital infrastructure that supports everyday life.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error