The Hook Lab / Tracker / North America / United States / Vantage Reno Updated 2026-11-25
Tracker · United States · NV

Vantage Reno

Vantage Data Centers · Reno, NV

Planning lodgedchanged 2026-10-15
224 MWrequested
—offered
—energised
1 mowaiting since first filing
mediumconfidence · 3 sources
Market
United States · North America
Grid
not settled yet
Place
Reno, NV
Network
—
Announced
2025-07-16
Planning lodged
2026-10-15
First reported by
Vantage · no status given

Who is on it

Developer
Vantage Data Centers · connectcre.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-10-15date: document dateon or before
    stagePlanning lodged1 source
    • DCD press
      Two separate applications, from March and November last year, suggest Vantage Data Centers NV11, LLC and Vantage Data Centers NV12, LLC are looking to develop a site at the southeast corner of Electric Avenue and USA Parkway.
  2. 2025-07-16
    stageAnnouncedconfirmed
    • DCD press
      The company this week announced its entry into the Nevada market with a 224MW campus in Storey County just outside of Reno.
    • connectcre.com press
      Data center developer Vantage Data Centers is entering the Reno, Nevada, area with a $3 billion investment in the development of a 224MW AI data center campus, NV1.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.