The Hook Lab / Tracker / North America / United States / Vantage Reno
Updated 2026-11-25
Tracker · United States · NV
Vantage Reno
Vantage Data Centers · Reno, NV
Planning lodgedchanged 2026-10-15
224 MWrequested
—offered
—energised
1 mowaiting since first filing
mediumconfidence · 3 sources
- Market
- United States · North America
- Grid
- not settled yet
- Place
- Reno, NV
- Network
- —
- Announced
- 2025-07-16
- Planning lodged
- 2026-10-15
- First reported by
- Vantage · no status given
Who is on it
- Developer
- Vantage Data Centers · connectcre.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-10-15date: document dateon or before
stagePlanning lodged1 source
- DCD press
Two separate applications, from March and November last year, suggest Vantage Data Centers NV11, LLC and Vantage Data Centers NV12, LLC are looking to develop a site at the southeast corner of Electric Avenue and USA Parkway.
- DCD press
-
2025-07-16
stageAnnouncedconfirmed
- DCD press
The company this week announced its entry into the Nevada market with a 224MW campus in Storey County just outside of Reno.
- connectcre.com press
Data center developer Vantage Data Centers is entering the Reno, Nevada, area with a $3 billion investment in the development of a 224MW AI data center campus, NV1.
- DCD press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.