The Hook Lab / Tracker / North America / United States / Southeast Wyoming data centre campus Updated 2026-11-25
Tracker · United States · WY

Southeast Wyoming data centre campus

Google · Southeast Wyoming, WY

Announcedchanged 2026-11-05
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
Market
United States · North America
Grid
not settled yet
Place
Southeast Wyoming, WY
Network
—
Announced
2026-11-05
First reported by
Crusoe · planned
Dates it gives
site acquired by Google 2026-11-06

Who is on it

Owner
Google · crusoe.ai
Developer
Crusoe · crusoe.ai

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-11-05
    stageAnnouncedconfirmed
    • blog.google primary
      Today, we are announcing our first data center in the state of Wyoming, in partnership with Tallgrass Energy, Black Hills Energy, American Electric Power (AEP), and Related Digital.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error