Auburndale Technology Center
Hillwood Development Company · 810 Pace Road, Auburndale, Polk County, FL
Planning approvedchanged 2026-11-04
700 MWrequested
—offered
—energised
1 mowaiting since first filing
mediumconfidence · 5 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- 810 Pace Road, Auburndale, Polk County, FL
- Network
- —
- Announced
- 2026-11-04
- Planning lodged
- 2026-11-04
- Planning approved
- 2023-12-18
- First reported by
- tampabay28.com · approved
- Dates it gives
- industrial PUD approved 2023-12-18
building permit application filed 08-14 (year not read)
site plan application 2026-11-04
first two buildings by 2029
Who is on it
- Owner
- Hillwood · newsbreak.com
- Developer
- Lincoln Property Company · newsbreak.com
Timeline
2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-11-04
stageAnnouncedautomatedconfirmed
- How Auburndale Approved a Data Center in Polk County Without Ever Saying It Out Loud - NewsBreak press
On Nov. 4, the Auburndale Technology Center announced itself as a data center.
- Emera (EMA) Q3 2026 Earnings Call Transcript - AOL press
Tampa Electric is working towards signing a contract by year-end for the first 350 megawatts or the Auburndale Technology Center that was announced by Hillwood Corporation earlier this week.
- How Auburndale Approved a Data Center in Polk County Without Ever Saying It Out Loud - NewsBreak press
-
2026-11-04
stagePlanning lodged1 source
- tampabay28.com press
A commercial building permit application filed with the City of Auburndale on August 14 provides additional details about the first phase.
- tampabay28.com press
-
2023-12-18
stagePlanning approvedconfirmed
- tampabay28.com press
Both zoning and Future Land Use requests were approved.
- baynews9.com press
City leaders approved several industrial uses for the 75-acre property on Pace Road in 2023, allowing a data center to be built there.
- tampabay28.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.