Cochise Supercomputer Campus
Tombstone Resources · near Cochise and the Apache Generating Station, Cochise County, AZ
Connection appliedchanged 2026-11-06
6,000 MWrequested
—offered
—energised
1 mowaiting since first filing
highconfidence · 3 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- near Cochise and the Apache Generating Station, Cochise County, AZ
- Network
- —
- Planning lodged
- 2026-11-06
- Connection applied
- 2026-11-03
- First reported by
- kjzz.org · application lodged
- Dates it gives
- community meeting 2026-11-04
county planning hearing set for 12-09
Who is on it
- Developer
- Tombstone Resources LLC · kjzz.org
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-11-06date: document dateon or before
stagePlanning lodgedconfirmed
- cochise.az.gov primary
Cochise County Development Services has received a Special Use Authorization application (SU26-22) from Tombstone Resources L.L.C. for a proposed supercomputer and artificial intelligence (AI) data center campus and Battery Energy Storage System (BESS) on approximately 747 acres along U.S. Highway 191 near Cochise, Arizona.
- cochise.az.gov primary
-
≤ 2026-11-03date: document dateon or before
conditionContested1 sourcecommunity opposition
- kjzz.org press
Over 1,000 people have signed a petition protesting the proposal and calls to write in comments opposing the project to Cochise County Development Services are making rounds on social media.
- kjzz.org press
-
≤ 2026-11-03date: document dateon or before
stageConnection applied1 source
- kjzz.org press
The applicant is requesting wholesale power generation and transmission services from AEPCO and retail electric services from the Sulphur Springs Valley Electric Cooperative (SSVEC).
- kjzz.org press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.