The Hook Lab / Tracker / North America / United States / Cochise Supercomputer Campus Updated 2026-11-25
Tracker · United States · US-OTHER · AZ

Cochise Supercomputer Campus

Tombstone Resources · near Cochise and the Apache Generating Station, Cochise County, AZ

Connection appliedchanged 2026-11-06
6,000 MWrequested
—offered
—energised
1 mowaiting since first filing
highconfidence · 3 sources
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
near Cochise and the Apache Generating Station, Cochise County, AZ
Network
—
Planning lodged
2026-11-06
Connection applied
2026-11-03
First reported by
kjzz.org · application lodged
Dates it gives
community meeting 2026-11-04
county planning hearing set for 12-09

Who is on it

Developer
Tombstone Resources LLC · kjzz.org

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-11-06date: document dateon or before
    stagePlanning lodgedconfirmed
    • cochise.az.gov primary
      Cochise County Development Services has received a Special Use Authorization application (SU26-22) from Tombstone Resources L.L.C. for a proposed supercomputer and artificial intelligence (AI) data center campus and Battery Energy Storage System (BESS) on approximately 747 acres along U.S. Highway 191 near Cochise, Arizona.
  2. ≤ 2026-11-03date: document dateon or before
    conditionContested1 sourcecommunity opposition
    • kjzz.org press
      Over 1,000 people have signed a petition protesting the proposal and calls to write in comments opposing the project to Cochise County Development Services are making rounds on social media.
  3. ≤ 2026-11-03date: document dateon or before
    stageConnection applied1 source
    • kjzz.org press
      The applicant is requesting wholesale power generation and transmission services from AEPCO and retail electric services from the Sulphur Springs Valley Electric Cooperative (SSVEC).

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.