The Hook Lab / Tracker / North America / United States / AVAIO Project Hercules Updated 2026-11-25
Tracker · United States · PJM · VA

AVAIO Project Hercules

AVAIO Digital Partners · Appomattox Center for Business and Commerce, off US 460 and VA 26, Appomattox County, VA

Planning approvedContestedcommunity oppositionchanged 2026-10-05
300 MWrequested
—offered
—energised
—waiting: no filing date on record
highconfidence · 4 sources
Market
United States · North America
Grid
PJM · PJM
Place
Appomattox Center for Business and Commerce, off US 460 and VA 26, Appomattox County, VA
Network
—
Announced
2024-12
Planning approved
2026-10-05
First reported by
Cardinal News · approved
Dates it gives
announced 2024-12-10
DEQ stormwater plan approved and construction expected by end of 2026 (reported 2026-10-05)
first building 2029

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-10-05date: document dateon or before
    conditionContested1 sourcecommunity opposition
    • Cardinal News press
      There is community opposition to the project, including a petition with close to 300 signatures that was started in March.
  2. ≤ 2026-10-05date: document dateon or before
    stagePlanning approved1 source
    • Cardinal News press
      the state Department of Environmental Quality has approved the company’s stormwater management plan
  3. 2024-12
    stageAnnouncedconfirmed
    • appomattoxcountyva.gov primary
      The project was publicly announced in December 2024, and the Governor of Virginia was quoted in that announcement, making the project public for well over a year.
    • Cardinal News press
      In 2024, the county’s economic development authority signed an agreement with AVAIO to start the development process on the $3 billion data center campus, according to a news release from the company.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.