The Hook Lab / Tracker / North America / United States / Google Van Buren Township data centre Updated 2026-11-25
Tracker · United States · MI

Google Van Buren Township data centre

Google · Van Buren Township, MI

Connection offeredchanged 2026-10-19
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
Market
United States · North America
Grid
not settled yet
Place
Van Buren Township, MI
Network
—
Planning approved
2026-10-19
Connection offered
2025-12-17
First reported by
Google · planned

Who is on it

Developer
Panattoni · planetdetroit.org

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-10-19date: document dateon or before
    stagePlanning approved1 source
    • planetdetroit.org press
      Van Buren Township Planning Commission approved final site plans for Google's 1-gigawatt data center and accompanying utility substation on 282 acres north of I-94.
  2. 2025-12-17
    stageConnection offeredconfirmed
    • sec.gov primary
      Company and Customer entered into that certain Primary Supply Agreement, dated as of December 17, 2025

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error