The Hook Lab / Tracker / Europe / Germany
Updated 2026-11-25
Tracker · Germany
Who's connected. Who's waiting. Who's gone.
23projects0with a sourced history—requested · projects with history
GridDE Germany (50Hertz, Amprion, TenneT, TransnetBW) · 0Germany is in progress: 23 projects, none with a sourced history yet.
| Evidence | Owner | Place | Grid | Status | 20202022202420262028 | Source | Details | |||
|---|---|---|---|---|---|---|---|---|---|---|
| Data Center Rote Burg FreyensteinIn development | Freyenstein, Wittstock/Dosse | DE | 720 MW | Planned | datacenter-insider.de1 source | |||||
| Project JupiterIn development | Lichterfeld-Schacksdorf | DE | 500 MW | Planned | entwicklungsstadt.de1 source | |||||
| NTT Frankfurt 6 (NTT FRA6)In development | former US barracks site, Rheinhessen | DE | 482 MW | Planned | hardwareluxx.de1 source | |||||
| Frankfurt (Oder) hyperscale data centreIn development | Markendorf industrial estate, Frankfurt (Oder) | DE | 330 MW | Planned | datacenter-insider.de1 source | |||||
| Virtus Wustermark data centreIn development | Wustermark | DE | 300 MW | Planned | connect-professional.de1 source | |||||
| Data Center Campus LübbenauIn development | Lübbenau/Spreewald | DE | 200 MW | Planned | datacenter-insider.de1 source | |||||
| Data4 Hanau campusIn development | Hanau (former Großauheim military base) | DE | 180 MW | Under construction | DCD1 source | |||||
| SDC Capital Trebbin data centreIn development | Trebbin | DE | 180 MW | Paused | entwicklungsstadt.de1 source | |||||
| NTT Brieselang data centre campusIn development | Brieselang, Havelland | DE | 96 MW | Planned | datacenter-insider.de1 source | |||||
| Stack Infrastructure Frankfurt data centreIn development | Frankfurt | DE | 80 MW | Under construction | DCD1 source | |||||
| Frankfurt 4 Data Center (NTT FRA4)Operating | Hattersheim am Main | DE | 70.4 MW34.4 live | Operating | NTT DATA1 source | |||||
| Colt Frankfurt 3 data centreIn development | Sossenheim, Frankfurt | DE | 32.4 MW | Under construction | coltdatacentres.net1 source | |||||
| Vantage Berlin II Campus (BER2)In development | Mittenwalde | DE | 32 MW | Under construction | entwicklungsstadt.de1 source | |||||
| noris Datacenter FRA1In development | Schwalbach bei Frankfurt | DE | 30 MW | Under construction | digitalbusiness-magazin.de1 source | |||||
| Industrial AI Cloud TucherparkIn development | Tucherpark, Munich | DE | 24 MW | Under construction | stmwi.bayern.de1 source | |||||
| Penta Infra Munich data centerIn development | Munich | DE | 20 MW | Planned | penta-infra.com1 source | |||||
| NTT Berlin 1 Data CenterOperating | Berlin | DE | 17.1 MW | Operating | NTT DATA1 source | |||||
| Portus Hamburg expansion data centre (HH4)In development | Hamburg | DE | 12.8 MW | Planned | portusdatacenters.com1 source | |||||
| HAM002Operating | Ahrensburg, Carl-Backhaus-Straße 21C | DE | 11.2 MW | Operating | atlasedge.com1 source | |||||
| Penta Infra DUS01 (Düsseldorf data center campus)Operating | Düsseldorf | DE | 9.5 MW2.4 live | Operating | penta-infra.com1 source | |||||
| Portus Data Centers MUC2 (Munich 2)In development | Munich | DE | 7 MW | Under construction | datacenter-insider.de1 source | |||||
| Portus MunichOperating | Kirchheim | DE | 7 MW | Operating | portusdatacenters.com1 source | |||||
| Data & AI Center for BerlinIn development | Berlin-Adlershof | DE | 5 MW | Planned | mdc-berlin.de1 source | |||||
| No projects match. | ||||||||||
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
23 projects, 0 with a sourced history. Every project has a page: what its first source reported, and each step of its history with the source and quote it rests on, marked confirmed (a primary source, or two sites) or 1 source. MW totals count projects with a history; medians use confirmed dates only.
No register lists every data centre, so this one grows from public sources. Know a project that is missing, or see an error? Tell us, with a link to a public source.
Comparables
0projects
—planning lodged → approved · n=0
—application → offer · n=0
—offer → first power · n=0
—planning lodged → first power · n=0