The Hook Lab / Tracker / Europe / Sweden Updated 2026-11-25
Tracker · Sweden

Who's connected. Who's waiting. Who's gone.

13projects0with a sourced history—requested · projects with history

GridSE Sweden (Svenska kraftnät) · 0Sweden is in progress: 13 projects, none with a sourced history yet.

Phase
Size
Owner

13 projects

Evidence OwnerPlaceGrid Status
20202022202420262028
SourceDetails
Meta Luleå campusIn development Luleå SE 723 MW Under construction theguardian.com1 source
EcoDataCenter 2 (Kvarnsveden campus)In development Kvarnsveden, Borlänge SE 600 MW Under construction ecodatacenter.tech1 source
SWE04 Sollefteå mega siteIn development Sollefteå (Hamre Industrial Park, Långsele) SE 300 MW Planned atnorth.com1 source
Google Horndal data centreIn development Horndal SE 150 MW Under construction theguardian.com1 source
EcoDataCenter FalunIn development Falun SE 80 MW Under construction theguardian.com1 source
Microsoft Sweden Central - GävleIn development Gävle SE 60 MW Under construction theguardian.com1 source
AWS Stockholm - EskilstunaIn development Eskilstuna SE 40 MW Under construction DCD1 source
SWE02 Stockholm metro data centerIn development Stockholm SE 30 MW Planned DCD1 source
Stockholm 4 SouthOperating Stockholm SE 28 MW Operating conapto.com1 source
STO01 Stockholm SE 18 MW Status not stated STACK Infrastructure1 source
SWE01Operating since 2022 Kista, Stockholm SE 12 MW12 live Operating DCD1 source
Vaultica Stockholm data centreIn development Upplands Väsby, Stockholm County SE 12 MW Planned finanstid.se1 source
Scandinavian Data Centers Eskilstuna data centreIn development Eskilstuna SE 10 MW Under construction techtidningen.se1 source
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

13 projects, 0 with a sourced history. Every project has a page: what its first source reported, and each step of its history with the source and quote it rests on, marked confirmed (a primary source, or two sites) or 1 source. MW totals count projects with a history; medians use confirmed dates only.

No register lists every data centre, so this one grows from public sources. Know a project that is missing, or see an error? Tell us, with a link to a public source.

Comparables

0projects
—planning lodged → approved · n=0
—application → offer · n=0
—offer → first power · n=0
—planning lodged → first power · n=0