The Hook Lab / Tracker / Europe / Sweden
Updated 2026-11-25
Tracker · Sweden
Who's connected. Who's waiting. Who's gone.
13projects0with a sourced history—requested · projects with history
GridSE Sweden (Svenska kraftnät) · 0Sweden is in progress: 13 projects, none with a sourced history yet.
| Evidence | Owner | Place | Grid | Status | 20202022202420262028 | Source | Details | |||
|---|---|---|---|---|---|---|---|---|---|---|
| Meta Luleå campusIn development | Luleå | SE | 723 MW | Under construction | theguardian.com1 source | |||||
| EcoDataCenter 2 (Kvarnsveden campus)In development | Kvarnsveden, Borlänge | SE | 600 MW | Under construction | ecodatacenter.tech1 source | |||||
| SWE04 Sollefteå mega siteIn development | Sollefteå (Hamre Industrial Park, Långsele) | SE | 300 MW | Planned | atnorth.com1 source | |||||
| Google Horndal data centreIn development | Horndal | SE | 150 MW | Under construction | theguardian.com1 source | |||||
| EcoDataCenter FalunIn development | Falun | SE | 80 MW | Under construction | theguardian.com1 source | |||||
| Microsoft Sweden Central - GävleIn development | Gävle | SE | 60 MW | Under construction | theguardian.com1 source | |||||
| AWS Stockholm - EskilstunaIn development | Eskilstuna | SE | 40 MW | Under construction | DCD1 source | |||||
| SWE02 Stockholm metro data centerIn development | Stockholm | SE | 30 MW | Planned | DCD1 source | |||||
| Stockholm 4 SouthOperating | Stockholm | SE | 28 MW | Operating | conapto.com1 source | |||||
| STO01 | Stockholm | SE | 18 MW | Status not stated | STACK Infrastructure1 source | |||||
| SWE01Operating since 2022 | Kista, Stockholm | SE | 12 MW12 live | Operating | DCD1 source | |||||
| Vaultica Stockholm data centreIn development | Upplands Väsby, Stockholm County | SE | 12 MW | Planned | finanstid.se1 source | |||||
| Scandinavian Data Centers Eskilstuna data centreIn development | Eskilstuna | SE | 10 MW | Under construction | techtidningen.se1 source | |||||
| No projects match. | ||||||||||
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
13 projects, 0 with a sourced history. Every project has a page: what its first source reported, and each step of its history with the source and quote it rests on, marked confirmed (a primary source, or two sites) or 1 source. MW totals count projects with a history; medians use confirmed dates only.
No register lists every data centre, so this one grows from public sources. Know a project that is missing, or see an error? Tell us, with a link to a public source.
Comparables
0projects
—planning lodged → approved · n=0
—application → offer · n=0
—offer → first power · n=0
—planning lodged → first power · n=0