The Hook Lab / Tracker / Europe / Sweden / EcoDataCenter 2 (Kvarnsveden campus) Updated 2026-11-25
Tracker · Sweden · SE

EcoDataCenter 2 (Kvarnsveden campus)

EcoDataCenter · Kvarnsveden, Borlänge

Under construction
600 MWplanned
—live
1source
Market
Sweden · Europe
Grid
SE · Sweden (Svenska kraftnät)
Place
Kvarnsveden, Borlänge
Owner
EcoDataCenter
Dates the source gives
construction began 2025-09
first phase completion planned mid-2027
Source
ecodatacenter.tech

From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.

Report an error