Tracker · Finland
Who's connected. Who's waiting. Who's gone.
10projects0with a sourced history—requested · projects with history
GridFI Finland (Fingrid) · 0Finland is in progress: 10 projects, none with a sourced history yet.
| Evidence | Owner | Place | Grid | Status | 20202022202420262028 | Source | Details | |||
|---|---|---|---|---|---|---|---|---|---|---|
| CSC Kajaani Data CenterOperating | Kajaani, Renforsin Ranta business park | FI | 900 MW | Operating | investinfinland.com1 source | |||||
| FIN04 Myllykoski mega siteIn development | Myllykoski, Kouvola | FI | 430 MW | Planned | atnorth.com1 source | |||||
| Hyperco Lohja data centerIn development | Lohja | FI | 300 MW | Planned | DCD1 source | |||||
| Hepokorpi data centreIn development | Hepokorpi, Espoo | FI | 265 MW | Under construction | kuntamonitori.fi1 source | |||||
| Kajaani-Otanmäki data centreIn development | Otanmäki, Kajaani | FI | 176 MW | Under construction | kuntamonitori.fi1 source | |||||
| Hyperco second data center in Koria, KouvolaIn development | Kouvola, Koria | FI | 100 MW | Application lodged | DCD1 source | |||||
| FIN02 Helsinki metro siteOperating | Sinimäentie, Espoo | FI | 40 MW | Operating | atnorth.com1 source | |||||
| Telia Helsinki Data CenterOperating | Helsinki | FI | 24 MW | Operating | telia.fi1 source | |||||
| XTX Markets Kajaani data centreIn development | Kajaani, Tihisenniemi | FI | 23 MW | Under construction | kuntamonitori.fi1 source | |||||
| Borealis Data Center, KajaaniOperating | Kajaani | FI | —10 live | Operating | sweco.fi1 source | |||||
| No projects match. | ||||||||||
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
10 projects, 0 with a sourced history. Every project has a page: what its first source reported, and each step of its history with the source and quote it rests on, marked confirmed (a primary source, or two sites) or 1 source. MW totals count projects with a history; medians use confirmed dates only.
No register lists every data centre, so this one grows from public sources. Know a project that is missing, or see an error? Tell us, with a link to a public source.
Comparables
0projects
—planning lodged → approved · n=0
—application → offer · n=0
—offer → first power · n=0
—planning lodged → first power · n=0