The Hook Lab / Tracker / Europe / Spain
Updated 2026-11-25
Tracker · Spain
Who's connected. Who's waiting. Who's gone.
40projects0with a sourced history—requested · projects with history
GridES Spain (Red Eléctrica) · 0Spain is in progress: 40 projects, none with a sourced history yet.
| Evidence | Owner | Place | Grid | Status | 20202022202420262028 | Source | Details | |||
|---|---|---|---|---|---|---|---|---|---|---|
| Merlin Navalmoral de la Mata data centreIn development | Navalmoral de la Mata, Cáceres | ES | 1,400 MW | Planned | merca2.es1 source | |||||
| Valdecaballeros data center campusIn development | Valdecaballeros, Badajoz Province | ES | 1,000 MW | Planned | DCD1 source | |||||
| Nostrum Data Center Badajoz (Evergreen)In development | Badajoz logistics platform, Badajoz | ES | 500 MW | Planned | hoy.es1 source | |||||
| BOX2BIT data centre in CariñenaIn development | Cariñena | ES | 400 MW | Planned | arainfo.org1 source | |||||
| Amazon Web Services data centre in Villanueva de GállegoIn development | Villanueva de Gállego | ES | 300 MW | Under construction | todoalicante.es1 source | |||||
| Azora data centre in Zaragoza (Aragón data processing centre)In development | Villamayor de Gállego | ES | 300 MW | Approved | azora.com1 source | |||||
| Bilbao-Arasur Campus (ARA 03)Operating | Arasur | ES | 300 MW24 live | Operating | ir.merlinproperties.com1 source | |||||
| DAMAC Toledo data centre | Toledo | ES | 227 MW | Status not stated | idp.es1 source | |||||
| Solaria Araba data centre projectIn development | Álava | ES | 225 MW | Planned | pello.eus1 source | |||||
| Green IT data centre in LuceniIn development | Luceni, Zaragoza | ES | 200 MW | Planned | arainfo.org1 source | |||||
| Puertollano artificial intelligence data centre (Solaria - Datasection)In development | Puertollano, Ciudad Real | ES | 200 MW | Planned | DCD1 source | |||||
| ACS and Benbros data centre, La Puebla de AlfindénIn development | La Puebla de Alfindén, Zaragoza | ES | 150 MW | Planned | DCD1 source | |||||
| Iberdrola and Echelon campusIn development | Madrid | ES | 144 MW | Planned | expansion.com1 source | |||||
| Álava data centreIn development | Álava | ES | 100 MW | Under construction | DCD1 source | |||||
| Alcalá Data CenterOperating | near Madrid-Barajas airport, Madrid | ES | 100 MW22.3 live | Operating | nabiax.com1 source | |||||
| Digital Realty and Merlin Properties Barcelona data centreIn development | Barcelona | ES | 100 MW | Planned | DCD1 source | |||||
| Panattoni Data Center BarcelonaIn development | Cerdanyola del Vallès | ES | 88 MW | Under construction | panattonieurope.com1 source | |||||
| DATA4 San Agustín del Guadalix campusIn development | San Agustín del Guadalix | ES | 80 MW | Under construction | DCD1 source | |||||
| Global Switch Madrid data centreIn development | Near Barajas airport, northwest Madrid | ES | 72 MW16 live | Planned | expansion.com1 source | |||||
| AQ-BCN1In development | Parc de l'Alba, Cerdanyola del Vallès | ES | 60 MW | Under construction | gsegroup.es1 source | |||||
| Alcalá de Henares data centreIn development | Alcalá de Henares | ES | 50 MW | Planned | DCD1 source | |||||
| DATA4 Madrid MAD01Operating | Alcobendas | ES | 50 MW | Operating | data4group.com1 source | |||||
| Microsoft data centre in Villamayor de Gállego | Villamayor de Gállego | ES | 50 MW | Status not stated | todoalicante.es1 source | |||||
| Nabiax Valencia data centreIn development | Valencia | ES | 50 MW | Planned | DCD1 source | |||||
| Ark Data Centres Barcelona data centreIn development | Barcelona, La Maquinista | ES | 45 MW | Planned | DCD1 source | |||||
| Edgnex Vicálvaro data centreIn development | Vicálvaro, Madrid | ES | 40 MW | Planned | DCD1 source | |||||
| Interxion (Digital Realty) Madrid campusIn development | Madrid | ES | 34 MW5 live | Under construction | DCD1 source | |||||
| Nostrum Zamudio data centreIn development | Zamudio, Biscay | ES | 30 MW | Application lodged | cronicavasca.elespanol.com1 source | |||||
| MAD 01 GetafeOperating | Getafe, Madrid | ES | 27 MW20 live | Operating | ir.merlinproperties.com1 source | |||||
| BCN 01 Zona Franca (Barcelona)Operating | Barcelona, Zona Franca | ES | 22 MW16 live | Operating | ir.merlinproperties.com1 source | |||||
| BCN1Operating | Sant Adrià de Besòs | ES | 14 MW | Operating | DCD1 source | |||||
| MAD01In development | San Blas-Canillejas district, Madrid | ES | 11.7 MW | Under construction | ituser.es1 source | |||||
| MAD-2 (San Fernando Park campus)In development | San Fernando Park campus, Madrid | ES | 10 MW | Planned | Iron Mountain1 source | |||||
| Templus Barcelona campusOperating | Barcelona | ES | 10 MW | Operating | DCD1 source | |||||
| Oxigen DC Montmeló data centreIn development | Montmeló, Barcelona province | ES | 9 MW | Planned | expansion.com1 source | |||||
| Equinix MD5 data centreIn development | Madrid | ES | 8.5 MW | Under construction | DCD1 source | |||||
| Barcelona data centre (BCN01)Operating | Barcelona, near Barcelona-El Prat airport | ES | 8.4 MW | Operating | EdgeConneX1 source | |||||
| Adam data centre in Parc de l'Alba SincrotróIn development | Cerdanyola del Vallès, Parc de l'Alba Sincrotró | ES | 8 MW | Under construction | digitalinside.es1 source | |||||
| Mediterra Montmeló data centreIn development | Montmeló, Barcelona province | ES | 8 MW | Planned | expansion.com1 source | |||||
| Fortinet Torija data centreOperating | Torija, Guadalajara | ES | 7 MW | Operating | dplnews.com1 source | |||||
| No projects match. | ||||||||||
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
40 projects, 0 with a sourced history. Every project has a page: what its first source reported, and each step of its history with the source and quote it rests on, marked confirmed (a primary source, or two sites) or 1 source. MW totals count projects with a history; medians use confirmed dates only.
No register lists every data centre, so this one grows from public sources. Know a project that is missing, or see an error? Tell us, with a link to a public source.
Comparables
0projects
—planning lodged → approved · n=0
—application → offer · n=0
—offer → first power · n=0
—planning lodged → first power · n=0