The Hook Lab / Tracker / Europe / Germany / Frankfurt (Oder) hyperscale data centre
Updated 2026-11-25
Tracker · Germany · DE
Frankfurt (Oder) hyperscale data centre
Frankfurt Data AI GmbH · Markendorf industrial estate, Frankfurt (Oder)
Planned
330 MWplanned
—live
1source
- Market
- Germany · Europe
- Grid
- DE · Germany (50Hertz, Amprion, TenneT, TransnetBW)
- Place
- Markendorf industrial estate, Frankfurt (Oder)
- Owner
- Frankfurt Data AI GmbH
- Dates the source gives
- Ziel 2026: Baurecht schaffen und Energieversorgung sichern
erster Bauabschnitt könnte 2027 begonnen werden - Source
- datacenter-insider.de
From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.