The Hook Lab / Tracker / Europe / Germany / Portus Data Centers MUC2 (Munich 2)
Updated 2026-11-25
Tracker · Germany · DE
Portus Data Centers MUC2 (Munich 2)
Portus Data Centers · Munich
Under construction
7 MWplanned
—live
1source
- Market
- Germany · Europe
- Grid
- DE · Germany (50Hertz, Amprion, TenneT, TransnetBW)
- Place
- Munich
- Owner
- Portus Data Centers
- Dates the source gives
- construction has begun
first capacity (5.5 MW) online planned end 2026 - Source
- datacenter-insider.de
From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.