Announcedchanged 2026-08-03
72 MWrequested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Manassas, VA
- Network
- —
- Announced
- 2026-08-03
- First reported by
- Yondr · planned
- Dates it gives
- site acquired 2026-08
ready for service expected 2029
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-08-03
stageAnnouncedconfirmed
- Yondr primary
Yondr Group, a global developer, owner and operator of hyperscale data centers has announced the acquisition of a 40-acre site in Manassas, Virginia in partnership with certain funds and accounts managed by Cerberus Capital Management, L.P. and its affiliates (“Cerberus”), a global leader in alternative investing.
- compute-atlas.com press
Cerberus Capital Management and Yondr Group announced the acquisition of a 40-acre site in Manassas for a 72 MW data center campus, with a 2029 ready-for-service date.
- Yondr primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.