xAI Colossus

xAI · Memphis, TN

Planning approvedPausedchanged 2026-04
—requested
—offered
—energised
9 mowaiting since first filing
mediumconfidence · 4 sources
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Memphis, TN
Network
—
Planning lodged
2026-03
Planning approved
2026-03
Planning lodged → approved
0 mo
First reported by
Data Center Frontier · operating

Who is on it

Network operator
Memphis Light, Gas & Water · datacenterfrontier.com
Builder
Dell Technologies · datacenterfrontier.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-04
    conditionPaused1 source
    • grokipedia.com press
      construction was paused in April 2026, with a commitment to resume by the first quarter of 2027
  2. 2026-03
    stagePlanning approved1 source
    • grokipedia.com press
      on March 11, 2026, the Mississippi Department of Environmental Quality (MDEQ) approved permits for 41 permanent methane gas turbines to replace the temporary units, enabling continued operation for Colossus expansions
  3. 2026-03
    stagePlanning lodged1 source
    • grokipedia.com press
      In early March 2026, xAI filed a $659 million construction permit for a new four-story, approximately 312,000 square foot building on a 79-acre parcel at 5414 Tulane Road in Memphis, adjacent to the existing Colossus 2 data center site.
  4. 2026-02
    conditionContested1 sourcecommunity opposition
    • grokipedia.com press
      On October 30, 2026, U.S. District Judge Debra M. Brown denied xAI's motion to dismiss the NAACP's Clean Air Act lawsuit over unpermitted gas turbines supplying Colossus 2, allowing the case to proceed.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.