The Hook Lab / Tracker / North America / United States / xAI Colossus
Updated 2026-11-25
Tracker · United States · US-OTHER · TN
xAI Colossus
xAI · Memphis, TN
Planning approvedPausedchanged 2026-04
—requested
—offered
—energised
9 mowaiting since first filing
mediumconfidence · 4 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- Memphis, TN
- Network
- —
- Planning lodged
- 2026-03
- Planning approved
- 2026-03
- Planning lodged → approved
- 0 mo
- First reported by
- Data Center Frontier · operating
Who is on it
- Network operator
- Memphis Light, Gas & Water · datacenterfrontier.com
- Builder
- Dell Technologies · datacenterfrontier.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-04
conditionPaused1 source
- grokipedia.com press
construction was paused in April 2026, with a commitment to resume by the first quarter of 2027
- grokipedia.com press
-
2026-03
stagePlanning approved1 source
- grokipedia.com press
on March 11, 2026, the Mississippi Department of Environmental Quality (MDEQ) approved permits for 41 permanent methane gas turbines to replace the temporary units, enabling continued operation for Colossus expansions
- grokipedia.com press
-
2026-03
stagePlanning lodged1 source
- grokipedia.com press
In early March 2026, xAI filed a $659 million construction permit for a new four-story, approximately 312,000 square foot building on a 79-acre parcel at 5414 Tulane Road in Memphis, adjacent to the existing Colossus 2 data center site.
- grokipedia.com press
-
2026-02
conditionContested1 sourcecommunity opposition
- grokipedia.com press
On October 30, 2026, U.S. District Judge Debra M. Brown denied xAI's motion to dismiss the NAACP's Clean Air Act lawsuit over unpermitted gas turbines supplying Colossus 2, allowing the case to proceed.
- grokipedia.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.