The Hook Lab / Tracker / North America / United States / Wagner Properties data centre Updated 2026-11-25
Tracker · United States · PJM · VA

Wagner Properties data centre

Wagner Properties · Petersburg, VA

Planning approvedchanged 2026-07-22
—requested
—offered
—energised
4 mowaiting since first filing
mediumconfidence · 3 sources
Market
United States · North America
Grid
PJM · PJM
Place
Petersburg, VA
Network
—
Planning lodged
2026-07-22
Planning approved
2026-04
First reported by
Data Center Frontier · planned
Dates it gives
reported 2026-07

Who is on it

Owner
Wagner Properties · richmondbizsense.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-07-22date: document dateon or before
    stagePlanning lodged1 source
    • Richmond BizSense press
      Wagner’s was approved in April, nearly two years after it was first submitted to the city.
  2. 2026-04
    stagePlanning approvedconfirmed
    • compute-atlas.com press
      Petersburg's interim planning director confirmed Wagner's site plan was approved in April 2026, nearly two years after first submission.
    • Richmond BizSense press
      Wagner’s was approved in April, nearly two years after it was first submitted to the city.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.