Viridian Janesville data centre

Viridian Partners · Janesville, WI

Paused
800 MWplanned
—live
1source
Market
United States · North America
Grid
MISO · MISO
Place
Janesville, WI
Owner
Viridian Partners
Dates the source gives
letter of intent expired 2026-06
referendum on the site 2026-11-03
Source
wpr.org

From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.