Updated 2026-11-25
Tracker · United States · PJM · OH
Viking Data Centers Akron
Viking Data Centers · Akron, OH
Announcedchanged 2021-09
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Akron, OH
- Network
- —
- Announced
- 2021-09
- First reported by
- Edison Electric Institute · planned
Timeline
20202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2021-09
stageAnnouncedconfirmed
- sec.gov primary
In September 2021, we entered into a Membership Interest Purchase Agreement and certain other auxiliary agreements (the “Ohio Mining Site Agreements”) with Viking Data Centers, LLC (“Viking Data Centers”) to jointly invest in the development of a cryptocurrency mining data center in Ohio (the “Ohio Mining Site”) with power capacity of up to 85 megawatts.
- sec.gov primary
today announced that it has entered into a Membership Interest Purchase Agreement and certain other auxiliary agreements (the “Agreements”) with Viking Data Centers, LLC (“Viking Data Centers”) to jointly invest in the development of a cryptocurrency mining data center space in Ohio (the “Ohio Mining Site”) with access to power capacity of up to 85 megawatts (“MW”).
- sec.gov primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.