The Hook Lab / Tracker / North America / United States / Vantage New Albany
Updated 2026-11-25
Tracker · United States · PJM · OH
Vantage New Albany
Vantage Data Centers · New Albany, OH
Under constructionchanged 2024-10-25
192 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- New Albany, OH
- Network
- —
- Construction started
- 2024-10-25
- First reported by
- Vantage · no status given
Who is on it
- Builder
- Turner Construction · vantage-dc.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2024-10-25
stageUnder constructionconfirmed
- Vantage primary
In recognition of Vantage’s entrance into New Albany, earlier today the company held a celebratory groundbreaking ceremony onsite to mark the start of construction.
- Vantage primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.