Townsite Solar 2 · Boulder City, Clark County, NV
Planning approvedContestedcommunity oppositionchanged 2026-06-23
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
- Market
- United States · North America
- Grid
- not settled yet
- Place
- Boulder City, Clark County, NV
- Network
- —
- Planning approved
- 2026-06
- First reported by
- GovTech · contested
- Dates it gives
- planning commission voted against 2026-05-20
federal land approval 2026-06-26
council voted to appeal 2026-07-14
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-06-23date: document dateon or before
conditionContested1 sourcecommunity opposition
- GovTech press
In Boulder City, hundreds of residents have voiced their opposition to construction of an AI data center on city-owned land there.
- GovTech press
-
2026-06
stagePlanning approvedconfirmed
- blm.gov primary
In June 2026, The Bureau of Land Management approved the Townsite Data Center project to construct, operate, and maintain a data center on 88.5 acres of public land in the vicinity of the existing Townsite Solar 1 project.
- blm.gov primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.