The Hook Lab / Tracker / North America / United States / TigerDC Project Spero Updated 2026-11-25
Tracker · United States · US-OTHER · SC

TigerDC Project Spero

TigerDC · Tyger River Industrial Park, Spartanburg County, SC

Announcedchanged 2026-01-26
100 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Tyger River Industrial Park, Spartanburg County, SC
Network
—
Announced
2026-01-26
First reported by
DCD · cancelled
Dates it gives
abandoned 2026-03

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-01-26
    stageAnnouncedconfirmed
    • postandcourier.com press
      New York-based TigerDC announced Jan. 26 it has plans to build a high-performance computing data center in the Tyger River Industrial Park – North, code-named Project Spero.
    • DCD press
      First announced last year, the $3 billion data center project passed its first reading in November.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.