TeraWulf Lake Hawkeye
TeraWulf · Lansing, NY
AnnouncedContestedplanning approvalchanged 2026-07-22
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- NYISO · NYISO
- Place
- Lansing, NY
- Network
- —
- Announced
- 2026-07-22
- First reported by
- TeraWulf · planned
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-07-22date: document dateon or before
conditionContested1 sourceplanning approval
- rochesterbeacon.com press
FLX Strong partnered with Cayuga Lake Environmental Action Now to file an Article 78 lawsuit against the Lansing Zoning Board of Appeals, TeraWulf, Cayuga Operating Co. LLC (a subsidiary of TeraWulf), Lake Hawkeye LLC, and Fred DelFavero, the project’s manager.
- rochesterbeacon.com press
-
≤ 2026-07-22date: document dateon or before
stageAnnounced1 source
- rochesterbeacon.com press
In its initial announcement, the company stated that acquiring land to start this project marked a major step forward in its expansion of high-performance computing and AI data center hosting.
- rochesterbeacon.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.