The Hook Lab / Tracker / North America / United States / TAC Data Centers Great Falls campus Updated 2026-11-25
Tracker · United States · MT

TAC Data Centers Great Falls campus

TAC Data Centers · north-east of Great Falls, Cascade County, MT

AnnouncedCancelledwithdrawn by proponentchanged 2026-07-28
600 MWrequested
—offered
—energised
—closed
mediumconfidence · 2 sources
Market
United States · North America
Grid
not settled yet
Place
north-east of Great Falls, Cascade County, MT
Network
—
Announced
2025-06-17
First reported by
montanaindependent.substack.com · planned
Dates it gives
announced 2025-06-17

Who is on it

Developer
TAC Data Centers · montanaindependent.substack.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-07-28date: document dateon or before
    conditionCancelled1 sourcewithdrawn by proponent
    • montanafreepress.org press
      By the fall, TAC Data Centers dropped its proposal, but the topic has remained relevant in the community.
  2. 2025-06-17
    stageAnnounced1 source
    • montanaindependent.substack.com press
      Announced on June 17, the data center is proposed for a 569-acre plot just outside of Great Falls’ northeast boundary.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error