The Hook Lab / Tracker / North America / United States / Sunnyside Road data centre
Updated 2026-11-25
Tracker · United States · PJM · PA
Sunnyside Road data centre
Catalyst Commercial Development · Sunnyside Road and Alberigi Drive, Jessup, Lackawanna County, PA
Planning lodgedchanged 2025-08-13
—requested
—offered
—energised
15 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Sunnyside Road and Alberigi Drive, Jessup, Lackawanna County, PA
- Network
- —
- Planning lodged
- 2025-08-13
- First reported by
- yahoo.com · application lodged
- Dates it gives
- land development application filed 13 August (year not shown)
Who is on it
- Developer
- Catalyst Commercial Development LLC · globaldatacenters.net
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2025-08-13
stagePlanning lodgedconfirmed
- globaldatacenters.net press
The Sunnyside Road application is dated August 13, 2025, six days before the council adopted the overlay rules on August 19.
- yahoo.com press
Catalyst Commercial Development LLC, the firm behind Breaker Street Associates, also wants to build a 487,000-square-foot data center near Sunnyside Road and Alberigi Drive, according to an Aug. 13 land development application and accompanying plans obtained via a Right to Know Law request.
- globaldatacenters.net press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.