The Hook Lab / Tracker / North America / United States / Spalding Investments data centre campus Updated 2026-11-25
Tracker · United States · US-OTHER · GA

Spalding Investments data centre campus

Spalding Investments LLC · Griffin, Spalding County, GA

Planning approvedContestedcommunity oppositionchanged 2025-11-01
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Griffin, Spalding County, GA
Network
—
Planning approved
2025-11-01
First reported by
DCD · approved
Dates it gives
approved 2025

Who is on it

Owner
Spalding Investments LLC · datacenterdynamics.com
Developer
Spalding Investments, LLC · griffindailynews.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2025-11-01date: document dateon or before
    conditionContested1 sourcecommunity opposition
    • griffindailynews.com press
      The approval also came despite opposition that included emotional pleas, a video showing the problems a data center elsewhere in Georgia has caused, an audio recording of how loud data centers can be, and a petition against the project with 289 signatures.
  2. ≤ 2025-11-01date: document dateon or before
    stagePlanning approved1 source
    • griffindailynews.com press
      The Spalding County Board of Commissioners unanimously approved the second data center development in the county at their zoning public hearing on Oct. 23.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.