The Hook Lab / Tracker / North America / United States / Sequoia Data Center
Updated 2026-11-25
Tracker · United States · CA
Sequoia Data Center
Cl-Santa Clara / LLC · 2600 De La Cruz Boulevard, Santa Clara, CA
Planning lodgedchanged 2019-08-14
—requested
—offered
—energised
87 mowaiting since first filing
mediumconfidence · 1 source
- Market
- United States · North America
- Grid
- not settled yet
- Place
- 2600 De La Cruz Boulevard, Santa Clara, CA
- Network
- —
- Planning lodged
- 2019-08-14
- First reported by
- California Energy Commission · approved
- Dates it gives
- exemption filed 2019-08-12
hearing on order granting it 2021-06-25
Timeline
201820202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2019-08-14
stagePlanning lodgedconfirmed
- California Energy Commission primary
On August 14, 2019, C1-Santa Clara, LLC (Sequoia Applicant) submitted the Sequoia Application.
- California Energy Commission primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.