The Hook Lab / Tracker / North America / United States / Sequoia Data Center Updated 2026-11-25
Tracker · United States · CA

Sequoia Data Center

Cl-Santa Clara / LLC · 2600 De La Cruz Boulevard, Santa Clara, CA

Planning lodgedchanged 2019-08-14
—requested
—offered
—energised
87 mowaiting since first filing
mediumconfidence · 1 source
Market
United States · North America
Grid
not settled yet
Place
2600 De La Cruz Boulevard, Santa Clara, CA
Network
—
Planning lodged
2019-08-14
First reported by
California Energy Commission · approved
Dates it gives
exemption filed 2019-08-12
hearing on order granting it 2021-06-25

Timeline

201820202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2019-08-14
    stagePlanning lodgedconfirmed

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error