The Hook Lab / Tracker / North America / United States / Sabey SDC Umatilla Updated 2026-11-25
Tracker · United States · US-OTHER · OR

Sabey SDC Umatilla

Sabey Data Centers · Umatilla, OR

Announcedchanged 2023-09-14
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Umatilla, OR
Network
—
Announced
2023-09-14
First reported by
Sabey · under construction
Dates it gives
Building 1 core and shell delivered 2026
Building 2 online 2029 or later

Who is on it

Owner
Sabey Data Centers · sabeydatacenters.com

Timeline

2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2023-09-14
    stageAnnouncedconfirmed
    • Sabey primary
      Sabey Data Centers, a premier designer, builder, and operator of multi-tenant data centers, is proud to announce that the company is expanding into Umatilla, Oregon. Sabey has purchased 60 acres to develop a 100+ MW state-of-the-art data center campus.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error