The Hook Lab / Tracker / North America / United States / Sabey SDC Quincy Updated 2026-11-25
Tracker · United States · US-OTHER · WA

Sabey SDC Quincy

Sabey Data Centers · Quincy, WA

Energisedchanged 2023-06
123 MWrequested
—offered
—energised
—closed
lowconfidence · 1 source
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Quincy, WA
Network
—
First power
2023-06
First reported by
Sabey · no status given

Who is on it

Operator
Sabey Data Centers · brightlio.com

Timeline

2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2023-06
    stageEnergised1 source

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error