Updated 2026-11-25
Tracker · United States · PJM · OH
Prologis Trenton data centre
Prologis · Trenton, Butler County, OH
Planning approvedchanged 2026-03-30
250 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Trenton, Butler County, OH
- Network
- —
- Planning approved
- 2026-03-30
- First reported by
- spectrumnews1.com · under construction
- Dates it gives
- voters approved a 25 MW cap on new data centres 2026-11-03
Who is on it
- Developer
- Prologis · spectrumnews1.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-03-30
stagePlanning approved1 source
- stopohiodatacenters.org press
Instead, the commission approved the site plan in under 10 minutes, with no questions taken from the public.
- stopohiodatacenters.org press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.