The Hook Lab / Tracker / North America / United States / Project Taurus
Updated 2026-11-25
Tracker · United States · US-OTHER · CO
Project Taurus
Raeden · 1615 W. Garden of the Gods Road, Colorado Springs, CO
Planning approvedchanged 2026-09-16
50 MWrequested
—offered
—energised
2 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- 1615 W. Garden of the Gods Road, Colorado Springs, CO
- Network
- —
- Planning lodged
- 2026-09-16
- Planning approved
- 2026-09-16
- Planning lodged → approved
- 0 mo
- First reported by
- coloradopolitics.com · contested
- Dates it gives
- planning commission approved 2026-07-23
council appeal vote set for 2026-09-17
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-09-16date: document dateon or before
stagePlanning approved1 source
- coloradopolitics.com press
July 23: The Planning Commission votes 6-2 to approve the data center plan with additional conditions on its utility usage and sound monitoring.
- coloradopolitics.com press
-
≤ 2026-09-16date: document dateon or before
stagePlanning lodged1 source
- coloradopolitics.com press
March 12: Raeden files first requests with city Planning Department for the Project Taurus data center development plan
- coloradopolitics.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.