The Hook Lab / Tracker / North America / United States / Project Sail
Updated 2026-11-25
Tracker · United States · US-OTHER · GA
Project Sail
Prologis · near Newnan, Coweta County, GA
Planning approvedchanged 2026-09-14
900 MWrequested
—offered
—energised
2 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- near Newnan, Coweta County, GA
- Network
- —
- Planning lodged
- 2026-09-14
- Planning approved
- 2026-04-07
- First reported by
- AJC · approved
- Dates it gives
- rezoning approved 2026-04-07
Who is on it
- Developer
- Atlas Development LLC · datacenterdynamics.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-09-14date: document dateon or before
stagePlanning lodged1 source
- DCD press
Atlas Development LLC, the company behind the scheme, has submitted a Development of Regional Impact (DRI) filing to the Georgia Department of Community Affairs, revealing details of the project.
- DCD press
-
2026-04-07
stagePlanning approved1 source
- fox5atlanta.com press
The Coweta County Board of Commissioners, in a 3-2 vote, approved the rezoning of 829 acres off Welcome to Sargent Road and Wagers Mill Road from Rural Conservation to Industrial.
- fox5atlanta.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.