The Hook Lab / Tracker / North America / United States / Project Peach Updated 2026-11-25
Tracker · United States · US-OTHER · GA

Project Peach

CyrusOne · near Palmetto (Johnston Circle, off SR 14), Coweta County, GA

Planning approvedchanged 2025-04-15
—requested
—offered
—energised
26 mowaiting since first filing
mediumconfidence · 2 sources
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
near Palmetto (Johnston Circle, off SR 14), Coweta County, GA
Network
—
Planning lodged
2024-10-03
Planning approved
2025-04-15
Planning lodged → approved
6 mo
First reported by
wabe.org · approved
Dates it gives
conditional rezoning approved 2025-04 (3-2
year from AJC 2025-05-08)
DRI lists completion 2036

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2025-04-15
    stagePlanning approved1 source
  2. 2024-10-03
    stagePlanning lodged1 source
    • nearbydatacenters.org press
      Project Peach filed for state regional review (DRI #4301): 2.1 million square feet in eight buildings.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.