The Hook Lab / Tracker / North America / United States / Project Peach
Updated 2026-11-25
Tracker · United States · US-OTHER · GA
Project Peach
CyrusOne · near Palmetto (Johnston Circle, off SR 14), Coweta County, GA
Planning approvedchanged 2025-04-15
—requested
—offered
—energised
26 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- near Palmetto (Johnston Circle, off SR 14), Coweta County, GA
- Network
- —
- Planning lodged
- 2024-10-03
- Planning approved
- 2025-04-15
- Planning lodged → approved
- 6 mo
- First reported by
- wabe.org · approved
- Dates it gives
- conditional rezoning approved 2025-04 (3-2
year from AJC 2025-05-08)
DRI lists completion 2036
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2025-04-15
stagePlanning approved1 source
- nearbydatacenters.org press
Coweta County commissioners approved the rezoning 3-2.
- nearbydatacenters.org press
-
2024-10-03
stagePlanning lodged1 source
- nearbydatacenters.org press
Project Peach filed for state regional review (DRI #4301): 2.1 million square feet in eight buildings.
- nearbydatacenters.org press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.