The Hook Lab / Tracker / North America / United States / Project Gravity
Updated 2026-11-25
Tracker · United States · PJM · PA
Project Gravity
Western Hospitality Partners · Archbald, Lackawanna County, PA
Planning lodgedchanged 2025-04
—requested
—offered
—energised
20 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Archbald, Lackawanna County, PA
- Network
- —
- Announced
- 2024-10
- Planning lodged
- 2025-04
- First reported by
- desmog.com · application lodged
- Dates it gives
- land purchase agreement 2024-10
conditional use permit pending 2026-03
Who is on it
- Owner
- Western Hospitality Partners · desmog.com
- Developer
- Archbald 25 Developer LLC · pa.gov
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2025-04
stagePlanning lodged1 source
- yahoo.com press
The developer submitted its sketch plan for the Archbald Planning Commission's April 2 meeting
- yahoo.com press
-
2024-10
stageAnnounced1 source
- desmog.com press
Western Hospitality Partners signed an agreement in October 2024 to buy the land for its Project Gravity data center project, according to the Lackawanna County Recorder of Deeds.
- desmog.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.