The Hook Lab / Tracker / North America / United States / PowerHouse Louisville Updated 2026-11-25
Tracker · United States · KY

PowerHouse Louisville

PowerHouse Data Centers · Louisville, KY

Planning approvedchanged 2026-07-15
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
Market
United States · North America
Grid
not settled yet
Place
Louisville, KY
Network
—
Announced
2025-01-17
Planning approved
2026-07-15
First reported by
PowerHouse · no status given

Who is on it

Owner
PowerHouse · datacenterdynamics.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-07-15date: document dateon or before
    stagePlanning approved1 source
    • louisvilledatacenter.com press
      This state-of-the-art, seven-building data center campus, which was approved by Louisville Metro Government’s Planning Commission
  2. 2025-01-17
    stageAnnounced1 source
    • DCD press
      AREP-owned PowerHouse this week revealed plans for a 400MW data center campus in Louisville alongside real estate firm Poe Companies.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.